Attachment 3: SBML - Submittal Register
Updated
A PDF document (298 KB) attached to Repair Taxiway Alpha & Bravo - North Auxiliary Airfield, from the Department of the Air Force. Due Dec 2, 2026, 12:00 PM (UTC-5).
File name: Attachment 3 - SBML 1052018 - Submittal Register.pdf
The full file is for paid members, or buy this bid alone.
Preview
Repair Taxiway
Alpha & Bravo
at
North Auxiliary Airfield
North, South Carolina
Orangeburg County
AF Form 66
Schedule of Material Submittals
April 21, 2017
100% Design Submittal
Project Manager: Greg Jones, P.E.
[email protected]
JBC Project No. SBML 12-1100
ADC Project No. 16222
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER
JBC SBML 12-1100
TO BE COMPLETED BY THE PROJECT ENGINEER
PROJECT TITLE
Repair Taxiway Alpha & Bravo
SOLICITATION/CONTRACT NO.
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
01 11 00, Para 1.4.2,
"Outage Requests"; G
01 11 00, Para 1.4.2, "Road
Closure Requests"; G
01 11 00, Para 1.4, "Work
Clearance"; G
01 14 00, Para 1.2.1.1, "List
of Contact Personnel"; G
01 30 00, Para 1.3.2,
"Resume for the proposed
Superintendent"; G
01 32 16.00 20, Para 1.2,
"Project Schedule"; G
01 32 16.00 20, Para 1.3.1,
"Initial Contract Progress
Report (AF IMT 3065)"; G
01 32 16.00 20, Para 1.3.2,
"Initial Contract Progress
Schedule (AF IMT 3064)"; G
01 32 16.00 20, Para 1.2.3,
"Project Schedule Updates";
G
01 32 16.00 20, Para 1.3.1,
"Monthly Contract Progress
Reports (AF IMT 3065)"; G
01 32 16.00 20, Para 1.3.2,
"Monthly Contract Progress
Schedules (AF IMT 3064)";
G
01 33 00, Para 1.7,
"Submittal Register"; G
01 35 13, Para 3.1.2, "Heavy
Equipment and Vehicle List"
01 35 13, Para 3.1.2,
"Existing Conditions Survey"
01 35 13, Para 3.1.2,
"Construction Operations
Plan"
AF Form 66
(a) As soon as possible but in no case later than 45 calendar days after NTP. (b) Prior to Final Inspection.
(c) Prior to Use.
(d) As Required.
OTHERS AS SPECIFIED
SD-11 CLOSEOUT SUBMITTALS
SD-10 OPERATION & MAINTENANCE
DATA
SD-09 MANUFACTURER'S FIELD
REPORTS
SD-08 MANUFACTURER'S
INSTRUCTIONS
SD-07 CERTIFICATES
SD-06 TEST REPORTS
SD-05 DESIGN DATA
SD-04 SAMPLES
(Ref spec & para no.)
SD-03 PRODUCT DATA
N
U
M
B
E
R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
SD-02 SHOP DRAWINGS
L
I
N
E
SD-01 PRECONSTRUCTION
SUBMITTALS
NO. OF COPIES REQUIRED
REQUIRED
DATE RECEIVED
SUBMISSION
IN CONTRACTING
DATE
DATE
TO
CIVIL
ENGINEERING
RETURN
SUSPENSE
DATE
FOLLOW UP
DATE CONTRACTOR
NOTIFIED
APPROVED
DISAPPROVED
CONTRACTOR
RESUBMITTAL
FINAL
APPROVAL
REMARKS
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER
JBC SBML 12-1100
TO BE COMPLETED BY THE PROJECT ENGINEER
PROJECT TITLE
The beginning of the document. Download the full file to read on.