Inyo National Forest, Facilities Improvement Project

Building Name / Location
Mt. Whitney Barracks

Task Description
Exterior Painting: Includes all surface preparations, siding and drywall repairs.

Unit

Quantity

SF

2000

Lone Pine, CA

Interior Painting: .Includes all surface preparations and drywall repairs.

SF

2000

Paint and Repair Main Entrance Ramp: Includes sanding and preparing ramp surfaces for painting. Wooden ramp & Metal railing).
Replace Bathroom Sinks: Replace existing sinks, including vanity.

LS

LS

Replace Back Stairs: Existing stairs are made of Doug Fir, approximately 4ft x 4ft replace-kind.

LS

Replace Kitchen Counter: Existing sink is approximately 24 inch by 72 inch (Laminate, Formica), replace inkind. Install New Bathroom Fan/Light Combo: Replace existing light and vent, with new fan/light combo. Must be vented to exterior.
Replace Ceiling Tiles: Existing ceiling tiles are made of Mineral Fiber, replace-kind.

LS

LS

SF

1600

Roof Replacement: Existing roof is made of composite shingles, replace in-kind.

SF

1600

Unit

Quantity

SF

1700

Building Name / Location
Mt. Whitney House

Task Description
Exterior Painting: Includes all surface preparations, siding and drywall repairs.

Lone Pine, CA

Interior Painting: .Includes all surface preparations and drywall repairs.

SF

1700

Remove Wood Stove: Includes drywall repair and ceiling/roof penetration repairs. Replace Kitchen Counter: Existing sink is approximately 24 inch by 72 inch (Laminate, Formica), replace inkind. Replace Double Sink

LS

LS

LS

Replace Faucet

LS

Install New Bathroom Fan/Light Combo: Replace existing light and vent, with new fan/light combo. Must be vented to exterior.

LS

Schedule of Work

Inyo National Forest, Facilities Improvement Project

Building Name / Location
Helitack Barracks

Task Description
Exterior Painting: Includes all surface preparations, siding and drywall repairs.

Unit

Quantity

SF

2000

Independence, CA

Interior Painting: .Includes all surface preparations and drywall repairs.

SF

2000

Replace Sink (Westside): Wall attachment sink, replace in-kind. Includes plumbing repairs. Replace Kitchen Counter: Existing counter is approximately 24 inch by 96 inch (Laminate, Formica), replace in-kind.
Replace Double Sink

LS

LS

LS

Replace Faucet

LS

Replace Vent Hood: Replace in-kind.
Install New Bathroom Fan/Light Combo: Replace existing light and vent, with new fan/light combo. Must be vented to exterior.
Paint Main Entrance Stairs and Backdoor Stairs: Existing wooden stairs are approximately 4ft x 4ft.

LS

LS

LS