Specifications
Birmingham Veterans Affairs Medical Center
700 South 19th Street
Birmingham, AL 35233
Renovate Wards 2k/2b For Optometry/Ophthalmology
Building #1
VA Contract No. 36C24724C0036
Station Project No. 521-24-102
Bancroft-AE Project No. 23-135
IFB Construction Documents Submittal
Vol 1 - Divisions 00-14
Vol 2 - Divisions 21-48
05/15/2026
Specifications
Birmingham Veterans Affairs Medical Center
700 South 19th Street
Birmingham, AL 35233
Renovate Wards 2k/2b For Optometry/Ophthalmology
Building #1
VA Contract No. 36C24724C0036
Station Project No. 521-24-102
Bancroft-AE Project No. 23-135
VOLUME 2
Divisions 21-48
DIVISION 21
FIRE SUPRESSION
Birmingham Veterans Affairs Medical Center
Birmingham, AL 35233
Renovate Wards 2k/2b For Optometry/Ophthalmology
Bancroft Architects + Engineers
11-1-16
SECTION 21 08 00
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section apply to all sections of Division 21. B. This project will have selected building systems commissioned.
The
complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.
The
commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS.
A
Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.
1.2 RELATED WORK
A. Section 01 00 00 GENERAL REQUIREMENTS.
B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
1.3 SUMMARY
A. This Section includes requirements for commissioning the Fire Suppression systems, subsystems and equipment.
This Section
supplements the general requirements specified in Section 01 91 00 General Commissioning Requirements.
B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.
1.4 DEFINITIONS
A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.
1.5 COMMISSIONED SYSTEMS
A. Commissioning of a system or systems specified in Division 21 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of Division 21, is required in cooperation with the VA and the
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Bid document
- Attachment 1: Experience Modification Rate Form
- Attachment 10: VHA Eye Clinic PCRA Signed CW
- Attachment 11: VHA Eye Clinic.5
- Attachment 2: VAAR 852.219-75
- Attachment 3: Past Performance Questionnaire -Past Performance Questionnaire
- Attachment 6: Invoicing
- Attachment 7: Invitation for Bids - Specifications Vol 1
- Bid document