SCOPE OF WORK

U.S. COAST GUARD

STATION CAPE CHARLES

CAPE CHARLES, VA 23310

SECTION 1 – GENERAL INFORMATION

1.1 BACKGROUND

Lift Station is the main source for waste water from Station Cape Charles.

1.2 SCOPE

The contractor must provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to provide sewage lift station pump out service at USCG Station Cape Charles located at 1 Marina Road, Cape Charles, VA 23310.

1.2.1 Technical Representative:

Name: Matthew D. Bowman (EPO)
PH: 757-505-9326
E-mail: [email protected]

SECTION 2 – SPECIFIC REQUIREMENTS/TASKS

2.1 GENERAL

Provide service to pump out approximately 2000GL per visit sewage offloads.

2.2 TASKS

• Pump out service requested on Monday, Wednesday, and Friday. • Work shall commence between the hours of 8am to 12pm
• Each visit the sewage lift station will be pumped to its lowest level possible (up to 2000GL) • In the event the contractor cannot service, the station Engineer Petty Officer (EPO) will be notified, and the service will commence as soon as possible.

2.3 CONTROL AND DISPOSAL OF WASTES

All wastes becomes the contractor’s property and shall be removed from the job site daily in accordance with all local, state, and federal environmental regulations.

2.4 SAFETY

During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by the Occupational Health and Safety Administration, 29CFR 1910 (series).

2.4.1 Unforeseen Hazardous Materials/Environmental Discharge:

If hazardous material is found during operations, stop that portion of work and notify both parties immediately at their listed point of contact. Within 14 calendar days, the government will determine fiscal indemnity without liability. If the material is not hazardous or poses no danger, the government will direct the cleanup and proceed without change. If the material is hazardous and handling of the material is necessary to accomplish the work, the government will issue a contract modification.

2.5 CONDITIONS AFFECTING THE WORK

The Offeror should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, the general and local conditions which can affect the cost of the work thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The government will assume no responsibility for any understanding or misrepresentations concerning conditions made by any of its officers or agents prior to