JC New Bed Tower IOTA
Project milestones and estimated dates
Project stage

Estimated timing

What this means for IOTA

SD1 review and SD2
design

Design kickoff: April 2027

SD2: FY27

Review existing plans and update furniture and
equipment layouts during design.

Design development

FY28

Equipment details and layout updates support
the design submissions.

Construction documents

FY28–FY29

Support design reviews and track equipment
and layout comments.

CUP, Motor Pool, Support
Bldg

Construction: FY27-FY33

Plan equipment delivery and building setup
around construction progress.

Bed Tower, OTP and East
Site

Construction: FY29–FY34

Plan equipment delivery and building setup
around construction progress.

Critical medical equipment

Review / lead time: FY32–FY34
Installation: FY34–FY35

The confirmed overall schedule will add more
detailed equipment dates.

CUP, Motor Pool, Support
Bldg Proposed BOD

February 2033 (FY33)

The USACE Area Office will set the timing after
reviewing project risks.

Bed Tower, OTP Proposed
BOD

October 2034 (FY35)

The USACE Area Office will set the timing after
reviewing project risks.

Source: 261001 - CFM CR IMS Schedules St. Louis. FY means fiscal year (October–September). CFM/USACE must confirm these estimates. All dates are subject to change as project progresses.