FORT BRAGG FUEL FACILITY SITE DATA ADDENDUM
1.
Site Maps : These site maps and schematics are provided to identify Government-furnished land and utilities described in PWS paragraph C-2.4.1. The Installation is responsible for removing pre-existing infrastructure prior to contract award. Area in the image is approximate. The easement will contain exact reference points. Figure 1: Bragg-East Site (Location #1)
Figure 2: 82nd Site (Location #2) Structures have been removed.
2.
Utility Maps: The area in yellow indicates the land area described in C-2.4.1 for services under this contract. The available utility runs are shown; communications (orange), electrical (red), stormwater (purple), and water (blue).Bragg-East (Location #1) Utilities Map is shown below. The area in gray was infrastructure removed prior to performance under this contract. The Installation is responsible for removing all pre-existing infrastructure. Figure 3: Utility Runs for East Bragg Site (Location #1)
Figure 4: Utility Runs for 82nd Site (Location #2)
Figure 6: 82nd Site Limitations - Location of protected old growth trees and potential space limitations are provided below. (see Table 1, Location 2, Site Specific Requirements)
85 ft
Potential space limitations
330 ft
442 ft
155 ft
Table-2: Annual Historical Throughput and Workload Table DFSP Bragg Summary Report- May 2024 to Apr 2025
Date+A7:Q46
Beginning
Inventory
Contract
Receipts
Stock
Transport
Total
Receipts
1 May 2024
2 Jun 2024
Jul 2024
4 Aug 2024
5 Sep 2024
6 Oct 2024
7 Nov 2024
8 Dec 2024
9 Jan 2025
10 Feb 2025
11 Mar 2025
12 Apr 2025
11024
29851
19413
29731
16693
23291
20314
31350
21908
15224
15163
23587
22884
15468
23749
23673
26802
7620
14511
24084
25742
16027
25843
15461
Total Annual Receipts for ULSD
29851
29731
23291
31350
15224
23587
15468
23673
7620
24084
16027
15461
255367
1 May 2024
2 Jun 2024
Jul 2024
4 Aug 2024
5 Sep 2024
6 Oct 2024
7 Nov 2024
8 Dec 2024
9 Jan 2025
10 Feb 2025
11 Mar 2025
12 Apr 2025
127094
N/A
23899
115692
N/A
47109
131172
N/A
55375
140975
N/A
31508
134955
N/A
23843
128935
N/A
71443
121847
N/A
60253
134382
N/A
32193
140729
N/A
63833
133474
N/A
56309
131499
N/A
56247
131612
N/A
79543
Total Annual Receipts for F24
23899
47109
55375
31508
23843
71443
60253
32193
63833
56309
56247
79543
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Attachment I - Ft Bragg COCO Performance Work Statement as of
- Attachment II - Past Performance Questionnaire Form
- Attachment III - PP Consent Form
- Attachment IV - Past Performance Reference List
- (Ft. Bragg)
- Bid document
- Amendment 6
- Attachment XI Services Performance Work Statement
- Attachment XII Fuel Facility Construction Addendum
- Ft Bragg Installation Design Guide (Condensed)