Schedule B
MACC Seed Project
Repair Dormitory Building 464

DKFX 1072201

Joint Base Lindsey Graham

N. Charleston, SC 29204

17-Sep-26
Item No

Description

Qty

Unit

0001
(Base)

All work required as per drawings and specifications
except as identified in line items 0002-0008 below.
Contractor shall provide a unit price and a total price.

LS

20,000
(EST)

LF

All work associated with removal and replacement of
deteriorated metal stud base or header channels. Price
0003
shall be based on an estimated quantity of 2,000 linear 2,000 (Option) feet of up to 6 inch wide, 25 gage metal channel. (EST)
Payment will be based on actual quantity installed.
Contractor shall provide a unit price and a total price.

LF

All work associated with removal and replacement of
deteriorated metal studs. Price shall be based on an
0002
estimated quantity of 20,000 linear feet of up to 6 inch (Option) wide, 25 gage metal studs. Payment will be based on actual quantity installed. Contractor shall provide a
unit price and a total price.

Hydrojet Domestic + Sanitary Sewer System branch
0004
lines and mains. Payment will be based on actual
(Option) quantity. Contractor shall provide a unit price and a total price.
Replace Bathroom (wet area) Drywall + Insulation
0005
Replacement. Payment will be based on actual
(Option) quantity installed. Contractor shall provide a unit price and a total price.
Replace Inoperable Ceiling Fans. Payment will be
0006
based on actual quantity installed. Contractor shall
(Option)
provide a unit price and a total price.

(EST)

LF

4,000
(EST)

SF

(EST)

EA

Install Electric Entry Door Hardware Set. Payment will
0007
be based on actual quantity installed. Contractor shall (Option)
provide a unit price and a total price.

(EST)

EA

Install Fire Extinguisher Cabinets. Payment will be
0008
based on actual quantity installed. Contractor shall
(Option)
provide a unit price and a total price.

(EST)

EA

Unit Price

Total

The beginning of the document. Download the full file to read on.