SECTION 01 33 00
SUBMITTAL PROCEDURES
JB Charleston (Dec 2021)
PART 1 GENERAL
SUMMARY
1.1.1 Submittal Information
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
Contractor's Quality Control (CQC) Manager shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified on the JB CHS Transmittal Form 4025.
Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
1.1.3 Submission of Submittals
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work), including but not limited to:
Certificates of insurance
Surety bonds
Lists of proposed Subcontractors
Lists of proposed products
Project Schedules
Submittal registers
Schedule of prices
Health and safety plans
Work plans
Quality Control (QC) plans
Environmental protection plans
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Solicitation
- Solicitation Attachment XU - Past Performance Customer Questionnaire
- Solicitation Attachment XV - Past Performance Survey
- Solicitation Attachment XW - JB Charleston MACC Work Load Estimate
- Solicitation Attachment XX - Task Order Proposal Request Seed Project
- Solicitation Attachment XY - On and Off-Ramp Procedures
- Statement of Work - JB CHS MACC
- Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A E)
- Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS Request for Information Form
- Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form (Submittal Register)
- Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form (Request for Information Register)
- Statement of Work - Attachment 14 - 01 35 26 - Attachment A Accident Investigation