RFQ 6913G627Q300002

Remediation and Restoration Activities

ATTACHMENT I

U.S. DEPARTMENT OF TRANSPORTATION

VOLPE NATIONAL TRANSPORTATION SYSTEMS CENTER

REMEDIATION AND RESTORATION ACTIVITIES

STATEMENT OF WORK

1.0 INTRODUCTION

Under an Interagency Agreement, the U.S. Department of Transportation John A. Volpe National Transportation Systems Center (Volpe Center) is providing support to the Federal Aviation Administration (FAA) Facilities Environmental Cleanup (ECU) Program. As part of this effort, a Remedial Action (RA) will be conducted at one facility in the FAA Eastern Service Area (ESA) to remove identified soil contamination.
1.1

SITE FOR CONTAMINATED SOIL REMEDIATION

The site requiring remediation for lead- and polychlorinated biphenyl (PCB)-contaminated soils is listed below:
1. QPI RCAG – Matawan, NJ (40.370895°, -74.220954°)

2.0 SITE ACTIVITIES

2.1

BACKGROUND

The FAA’s ECU Program has identified the potential for environmental and human health risks and/or liability associated with the facility above based on prior research, known historic operations and practices, and required cleanup actions. 2.2

TASKS TO BE PERFORMED

The Contractor shall conduct all work in accordance with Federal, State, and local requirements. Where inconsistencies exist, the Contractor shall follow the most stringent requirement. 2.2.1

Remediation and Restoration Work Plan

The Contractor shall submit a draft Remediation and Restoration work plan (Work Plan) (where applicable) within ten (10) business days of the project kick-off meeting that addresses the project requirements below.
This task involves the preparation and submission of a draft and final Work Plan. The Work Plan shall detail the technical approach and schedule for conducting all contaminated soil remediation, disposal, and site restoration activities described below. To assist with preparation of the Work Plan, the contractor shall thoroughly review the Government-furnished information (GFI) for pertinent information. The removal quantities and depths in the Preliminary Assessment/Site Investigation and Remedial Investigation reports (if provided) are to be used as a guide along with the estimated total quantities listed in this SOW Section 2.2.2.

RFQ 6913G627Q300002

Remediation and Restoration Activities
The Work Plan shall describe methods and procedures for performing soil remediation, disposal, and restoration. Disposal methods must be detailed by the contractor for the site. FAA has consulted a Licensed Site Remediation Professional (LSRP), and the LSRP will select and approve

The beginning of the document. Download the full file to read on.