Home / WY Np Yell 10(24), Grand Loop Road Norris to Golden Gate… / Document

Bid document

Updated

A PDF document (179 KB) attached to WY Np Yell 10(24), Grand Loop Road Norris to Golden Gate, Phase 3, from the Federal Highway Administration.

File name: QA_10-05-2026.pdf

Download the full documentSee the bid

The full file is for paid members, or buy this bid alone.

Preview

Project No.
Project

WY NP YELL 10(24)

Grand Loop Road Norris to Golden Gate, Phase 3

Question
Are the scaling quantities for the areas to be
scaled that are called out in the plans to be
factored into the lump sum amount under 651Rockfall Protection? Are the rock bolts and dowels to be installed at
the scaling locations?

Answer
An offer schedule will be developed for the
Task Order solicitation. Slope Scaling is
anticipated to be quantified by Hours
needed to perform the work.
Yes, Rock Bolts and Dowels are anticipated
at the slope scaling locations.
The Task Order is planned for solicitation
during the winter 2026/2027.
A Notice to Proceed date is being planned
for May 2027.

Check General or Technical

#

General

Technical

X

X

X

When will project specifications be published?

X

What is the anticipated NTP date for this
project?

Date
10/5/26

10/5/26
10/5/26
10/5/26

The beginning of the document. Download the full file to read on.

Other documents in this bid