DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

STATION SAND KEY

SPECIFICATIONS

FOR

Repair Fuel Lines & Tank

General: United States Coast Guard Station Sand Key requesting repair work to be completed on various fuel lines and fuel related systems. Location:
United States Coast Guard Station Sand Key.
1375 Gulf Boulevard
Clearwater, FL 33767
I. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Normal operating hours are from 0700 to 1700 Monday thru Friday except federal holidays. Any work during other hours unless otherwise instructed or permitted shall be scheduled and approved with the Contracting Officers Representative. II. Notification of Start and Completion of Work: The Contractor shall notify Coast Guard one week prior to start of work.
III. Coast Guard Contracting Officers Representative: The Contractor shall contact the COR to coordinate all construction efforts onboard Coast Guard Facilities. MKC Zachery Little

[email protected]

417-612-3258

IV: Recycling and Disposal of Refuse: Minor refuse, excess or waste materials resulting from construction operations may be disposed of in Station dumpsters. All disposals shall be done in accordance with federal, state, and local laws and regulations. V: Safety: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 Safety and Health Regulations for Construction. The contractor shall have a written safety plan as required in FAR 5.236-13. The plan shall unequivocally assign responsibility and authority for safety to the superintendent by name. Immediate notification to the Contracting Officer’s Representative of lost time due to accidents is required. Provide two copies of workman’s compensation accident reports by noon of the day following the accident. The Coast Guard reserves the right to bar any workers or supervisors from the premises should they be documented as violating set safety standards and regulations. VI. Inspection: The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the project specifications. Only the Contracting Officer or his/her representative may accept work performed by the contractor.
VII. Operations and Storage: The contractor is to take whatever steps necessary to ensure that his materials are protected. The Coast Guard has no responsibility for receipt,