CULVERT INSPECTION REPORT
HOLZWARTH CULVERT
HOLZWARTH ACCESS ROAD OVER COLORADO RIVER
ROCKY MOUNTAIN NATIONAL PARK
LOOKING WEST
STRUCTURE NO. 1520-029S
INSPECTION TYPE: ROUTINE
INSPECTION DATE: 10/1/2024
Report prepared by:
Federal Highway Administration
SOUTH (DOWNSTREAM) SIDE
FLH Office of Bridges and Structures
Bridge Inspection Program
22001 Loudoun County Parkway, Building E2, Suite 200
Ashburn, VA 20147
https://bridge.flhd.fhwa.dot.gov
STRUCTURE NO.
INSPECTION DATE:
STRUCTURE SUMMARY
HOLZWARTH CULVERT
1520-029S
10/01/2024
CULVERT IDENTIFICATION AND DESCRIPTION
STRUCT. TOTAL LENGTH: 38.7 FT (11.8 M)
YEAR RECONSTRUCTED:
LOCATION
ROCKY MOUNTAIN NATIONAL PARK
FEATURE INTERSECTED: COLORADO RIVER
INSPECTION TEAM:
MILE POINT: .. .00 (KM PT 0)
south of Timber Creek Campground.
Beyond locked gate.
D. Christensen, B. Dietrick, P. Sharifi
CONDITION ASSESSMENT:
Bill Dietrick
REPORT REVIEW:
Marcus Miller
REPORT APPROVAL:
Date: 01/30/2025
Jorgomai Ceesay
STRUCTURE EVALUATION SUMMARY
This six-barrel corrugated metal pipe culvert is in poor structural condition. Inspection findings include delaminating, spalling, and cracking of the headwalls; spalling and undermining of concrete at the bottom of both the upstream and downstream divider walls between barrels; severe corroding of the barrel inverts, with rust holes present; missing sections of barrel inverts, and torn and uplifted inverts at the upstream end of the barrels due to high flow impacts and corrosion; widespread barrel distortions resulting from invert section loss; undermining of barrels at the downstream end; and minor debris accumulation at the upstream divider walls and inside several barrels. In addition, previous inspection teams observed water piping around most of the barrels, particularly during highwater events.
In view of the poor condition of the culvert inverts and the loss of soil support due to undermining, there are concerns about the long-term stability of the structure, particularly during highwater events. A local informed the inspection team that the structure was overtopped in the spring of 2022. The upstream channel has poor alignment and is migrating to the east. Given the high cost of repairs and the evident lack of capacity of the barrels for high flow conditions, it is recommended that the structure be replaced in the near future.
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO.
1520-029S
HOLZWARTH CULVERT
10/01/2024
INSPECTION DATE :
B
PRIORITY OF IMPROVEMENT
A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.
The beginning of the document. Download the full file to read on.