McClellan Boiler Replacement Drawing Set Construction Draft

Updated

A PDF document (4.3 MB) attached to FY27 NRM - Replace B98 and B88 Boiler and Sump Pumps, from the Department of Veterans Affairs. Due Nov 3, 2026, 2:00 PM (UTC-8).

File name: McClellan B88 Boiler Replacement Drawing Set Construction_Draft.pdf

Download the full documentSee the bid

The full file is for paid members, or buy this bid alone.

Preview

A

A

U.S. Department of Veterans Affairs
Project Name:

BUILDING 88 BOILER & DOMESTIC WATER HEATER REPLACEMENT

B

R
AF

T

B

C

7/30/2026 4:09:01 PM

D

BUILDING 88

N
D

E

D

F

C:\Users\haung\Documents\McClellan B88 Boiler Replacement_haung3GHVP.rvt

E

C

CONSULTANTS

Revisions:

VA FORM 08 - 6231

New England Engineering, Inc.

30 Turnpike Road, Suite #1

Southborough, MA 01772
Phone: (508) 485-4633 Ext. 54
FAX:
(508) 485-1830

Date:

ARCHITECT/ENGINEER OF RECORD

F

KEY PLAN

Drawing Title

STAMP

Office of
Construction
and Facilities
Management

248 Copeland Street
Quincy, MA 02169
P: 617-481-6390
F: 617-687-5990

Phase

Project Number

BUILDING 88 BOILER & DOMESTIC

WATER HEATER REPLACEMENT

COVER SHEET

Building Number

Location
Drawing Scale
McClellan VA Clinic
5342 Dudley Boulevard, McClellan Park, CA 95652 N/A

Approved:

U.S. Department
of Veterans
Affairs

Project Title

Issue Date

Checked

Drawn

July 10, 2026

PFS

TM

Drawing Number

G-001

A

A

SCOPE OF WORK

GENERAL NOTES

DRAWING INDEX

THIS PROJECT ENCOMPASSES THE DECOMMISSIONING, REMOVAL, AND REPLACEMENT OF THE HEATING HOT WATER AND DOMESTIC WATER HEATING INFRASTRUCTURE AT THE MCCLELLAN VA CLINIC. THE SCOPE INCLUDES REPLACING THREE (3) EXISTING HEATING HOT WATER BOILERS WITH TWO (2) NEW 1,000 MBH DUAL-FUEL HIGH-EFFICIENCY BOILERS; AND REPLACING TWO (2) EXISTING DOMESTIC WATER HEATERS WITH TWO (2) NEW 120 MBH DUAL-FUEL HIGHEFFICIENCY UNITS.

1.

G-001
G-002
G-003
MD-101
MH-101
MH-102
MI-201
MI-401
PD-101
PQ-101
PQ-102
PI-201
PI-401
E-000
ED-010
ED-100
E-010
E-100

SURVEY: BEFORE ANY WORK IS STARTED, THE CONTRACTOR SHALL MAKE A THOROUGH SURVEY

WITH THE COR, OF AREAS OF BUILDINGS (INSIDE AND OUTSIDE) IN WHICH ALTERATIONS OCCUR AND AREAS WHICH ARE ANTICIPATED ROUTES OF ACCESS, AND FURNISH A REPORT, SIGNED BY BOTH,

TO THE CONTRACTING OFFICER. THIS REPORT SHALL LIST BY ROOMS AND SPACES, ETC:

THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, AND ENGINEERING SERVICES NECESSARY TO DELIVER A FULLY OPERATIONAL, INTEGRATED, COMMISSIONED, AND CODE-COMPLIANT HYDRONIC AND DOMESTIC HOT WATER PLANT. ALL WORK MUST COMPLY WITH APPLICABLE VA DESIGN STANDARDS, LOCAL CODES, AND ENVIRONMENTAL REGULATIONS.

A.

EXISTING CONDITION AND TYPES OF RESILIENT FLOORING, DOORS, WINDOWS, WALLS AND

OTHER SURFACES NOT REQUIRED TO BE ALTERED THROUGHOUT AFFECTED AREAS OF

BUILDINGS.

B.

EXISTENCE AND CONDITIONS OF ITEMS SUCH AS PLUMBING FIXTURES AND ACCESSORIES,

ELECTRICAL FIXTURES, EQUIPMENT, VENETIAN BLINDS, SHADES, ETC., REQUIRED BY