Building 88 and 98 Boiler & Domestic Water Heater Replacement McClellan VA Clinic

DEPARTMENT OF VETERANS

AFFAIRS

VHA MASTER SPECIFICATIONS

Section 00 01 10

SECTION NO

DIVISION AND SECTION TITLES

DATE

DIVISION 01 - GENERAL REQUIREMENTS

General Requirements

06-2026

01 32 16.15

Project Schedules (Small Projects – Design/Bid/Build

12-2025

01 33 23

Shop Drawings, Product Data, and Samples

03-2026

01 35 26

Safety Requirements for Major Projects

05-2024

01 42 19

Reference Standards

11-2020

01 45 00

Quality Control

01 45 35

Special Inspections

01 57 19

Temporary Environmental Controls

12-2020

Temporary Interior Signage

07-2015

Construction Waste Management

04-2022

Sustainable Construction Requirements

10-2017

General Commissioning Requirements

04-2022

01 74 19

01 81 13

01 91 00

AF

01 58 16

T

01 00 00

02-2021
06-2021

DIVISION 02 – EXISTING CONDITIONS

Demolition

D
R

02 41 00

08-2017

DIVISION 03 – CONCRETE

03 30 53

(Short-Form) Cast-in-Place Concrete

01-2021

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 92 00

Joint Sealants

04-2022

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41

Seismic Restraint Requirements for Non-Structural
Components

01-2021

DIVISION 22 – PLUMBING

22 05 11

Common Work Results for Plumbing

01-2023

22 05 12

General Motor Requirements for Plumbing Equipment

09-2020

22 05 19

Meters and Gages for Plumbing Piping

09-2020

Building 88 and 98 Boiler & Domestic Water Heater Replacement McClellan VA Clinic

22 05 23

General-Duty Valves for Plumbing Piping

09-2020

22 07 11

Plumbing Insulation

09-2019

22 08 00

Commissioning of Plumbing Systems

11-2016

22 11 23

Domestic Water Pumps

09-2015

22 31 11

Water Softeners

09-2015

22 34 00

Fuel-Fired Domestic Water Heaters

09-2020

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

Common Work Results for Boiler Plant

06-2024

23 05 11

Common Work Results for HVAC

03-2023

23 05 12

General Motor Requirements for HVAC and Steam
Generation Equipment

03-2023

23 05 41

23 05 93

23 07 11

23 08 00

23 09 23

23 11 23

23 21 11

23 21 13

23 52 16

DATE

Noise and Vibration Control for HVAC Piping and
Equipment

03-2023

Testing, Adjusting, and Balancing for HVAC

03-2023

HVAC and Boiler Plant Insulation

02-2020

Commissioning of HVAC Systems

03-2023

Direct-Digital Control System for HVAC

03-2023

Facility Natural-Gas Piping

04-2020

Boiler Plant Piping Systems

12-2025

Hydronic Piping

06-2025

Hydronic Pumps

03-2023

D
R

23 21 23

DIVISION AND SECTION TITLES

AF

SECTION NO

T

23 05 10

Condensing Boilers

DIVISION 26 – ELECTRICAL

26 05 11

Requirements for Electrical Installations

11-2022

26 05 19

Low-Voltage Electrical Power Conductors and Cables

11-2022