Misty Barge Request for Quotations Questions and responses
Updated
A PDF document (646 KB) attached to Misty Barge Dry Dock Services, from the Forest Service. Due Nov 9, 2026, 12:00 PM (UTC-9).
File name: C05 1240BF27Q0002 Misty Barge RFQ Questions and responses.pdf
The full file is for paid members, or buy this bid alone.
Preview
1240BF27Q0002, Misty Barge Dry Dock
A. Solicitation, Submission, and Schedule
1.
Schedule of Items workbook. The price workbook (C04-1240BX27Q0002-Scedule-of-ItemsOffer.xlsx) contains a second, hidden tab, "Sheet1," with unrelated pricing (custodial cleaning CLINs and Contract Manpower Reporting). The file name also reads 1240BX27Q0002 rather than 1240BF27Q0002. Please confirm:
a.
Only the BID SUMMARY SHEET tab is to be completed, and the hidden "Sheet1" tab is not to be completed and may be disregarded or deleted.
a. Government Response: The hidden sheet is not to be used and maybe discarded.
b.
The blank line below CLIN 0005 may be used for unit prices or other pricing information, or should be left blank.
a. Government Response: The space below CLIN 0005 is to be left blank.
Reference: Schedule of Items workbook
2.
Notice of award and the 30-day barge acceptance notice. SF 1449 shows a period of performance of November 10, 2026 to April 1, 2027, and PWS 1.4 shows date of award to April 1, 2027. PWS 3.2.3 requires a minimum 30-day notice of when the barge will be accepted at drydock. With quotations due October 30, the earliest the barge could be accepted after award is likely midDecember 2026 or later. Please confirm: a.
The anticipated award date, period of performance start date, and contract end date. a. Government Response: The government anticipates an award no later than 10 November 2026 with a period of performance to start on 10 November 2026/date of award. This start date allows the contractor to begin any performance needed prior to receiving the barge, to include preparing sites, ordering supplies etc.
b.
Whether the 30-day notice may be given in the quotation (as a proposed acceptance window) or must be given after award, and from what date the 30 days is counted. a. Government Response: This 30 day notice is to engage with contracting group to award the towing contract and notify the contractor once award is made. Yes, midDecember is a good estimate.
c.
The Government's anticipated towing window and towing contractor, if known. a. Government Response: Towing window is currently through Nov 30, 2026 with Cascade Towing. Timelines can be revised based on dry dock availability, but winter weather could cause delays.
d.
Whether the April 1, 2027 completion date applies to relaunch, or to tow-away from the contractor's facility.
a. Government Response: The government objective is to be relaunched by 01 April 2027.
e.