Navajo-Gallup Water
Supply Project (NGWSP)
Turnout Buildings Pre-Bid Conference Site Tour
August 26, 2026
Agenda
• Introduction
• NGWSP Overview
• Turnout Building Locations and Scope
• Procurement Requirements
• Travel Plan
• JHA
• Questions
• Adjourn
NGWSP Background
• Description
• Currently estimated at $2.4 Billion
• 2 Main Laterals (Cutter and San Juan) totaling 300 miles of Pipelines (20”-48”) • 2 Conventional Water Treatment Plants with ultimate capacity of 5 & 38 MGD • 19 Pumping Plants -- raw and finished water
• 13 Turnout Buildings
• Numerous Storage Tanks
• Construction began in June 2012
• Scheduled to end in December 2028
Project Overview Map
FCWR
Shiprock
Connection
Intake Pumping Plant
CLWTP
Reach 1
SJLWTP
San Juan
Lateral
Window
Rock
Cutter
Lateral
Block 2-3
Crownpoint
City of
Gallup
Operational
Completed
Under Construction
In Design
(As of February 2024)
Turnout Building Locations
Turnout Building Scope
• Precast concrete building
Contractor design, including
building, floor slab and
foundation
Building mechanical, electrical,
controls and security
• Pipe and valving
Connection to lateral distribution
pipe (supply)
Connection to cPWS distribution
pipe (delivery)
Interior exposed piping, valves,
and accessories
Buried piping, valves, and
accessories
•Sitework
Fenced site with gate
Buried thrust blocks
Gravel surfacing
Drainage
Access Roads
Coyote Canyon and Window Rock only
Low water crossing at BBN9
•Controls integration with existing San
Jaun Lateral SCADA System
•Fiber optic cable infrastructure
•Project Power
Transformer provided by NTUA
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Invitation for Bids NGWSP Turnout Buildings
- Sol
- Attachment 0 00 01 NGWSP TURNOUT BLDGS Specifications
- Attachment Small Business Subcontracting Plan
- Attachment Wage Determination Heavy - San Juan County NM
- Attachment Wage Determination Building - San Juan County NM
- Sol Amendment 0001
- Attachment 1 00 01 Specifications 0002
- Attachment 3 1 00 02B Corrosivity Report NGWSP Turnout Bldgs 0002
- Attachment 3 1 00 02A Test Pit Log 0002
- Attachment 7: Wage Determination Heavy - McKinley County NM 0002
- Attachment 8: Wage Determination Building - McKinley County NM 0002