SOLICITATION NUMBER: N40085-26-R-0262

This notice does NOT constitute a request for proposal, request for quote, or invitation for bid. The intent of this pre-solicitation synopsis is to make notice of a proposed contract action for performing pre-construction services and construction services for P-271, E-130J Main Operating & Training Base, Marine Corps Air Station (MCAS) Cherry Point, North Carolina.

PROJECT DESCRIPTION:

This project constructs all operational and support facilities for E-130J Main Operating Base (MOB) and Fleet Replacement Squadron (FRS) training campus at the Marine Corps Air Station (MCAS) in Cherry Point, NC. New construction facilities include an aircraft parking apron, aircraft access apron, taxiway, three-bay aircraft maintenance hangar, training building, Mobile Support Unit operational compound, and an aircraft maintenance and ground support equipment warehouse. Renovation of existing facilities includes Building 244 for Center for Naval Aviation Technical Training (CNATT) academic and applied training functions associated with the E130J. The Aircraft Maintenance Hangar will be a two-story building with high-bay, overhead maintenance space to support three E-130J aircraft. The hangar will be constructed as four separate buildings with expansion joints, built on deep foundations using driven precast, prestressed concrete piles.
The Hangar Security Building is a single-story security guard house, outside of the PL2 security fenceline, that provides controlled access to the hangar enclave for vehicles and pedestrians. The Training Building is a predominantly single-story building, divided into four massing areas with varying roof heights. Much of the facility is low-rise, with roof heights of 16-20 feet. The Mobile Support Unit Operational Compound is a low-rise, pre-engineered long-span metal building.
The Aircraft Maintenance and Ground Support Equipment (GSE) Warehouse is a low-rise, preengineered metal building with structural columns located along the middle of each space. The project will renovate and alter portions of Building 244 which has a total floor area of 4,356 m2 and currently supports existing CNATT functions.
The project also includes significant road widening along Roosevelt Avenue and Access Roads, utility upgrades including the replacement of an electric substation, water, sewer and communications lines and a pump station.
The completion time for this project is approximately 700 calendar days after award for preconstructions services and 1,825 calendar days for construction services.