Q&A 140L1726R0010

Q01: Amendment 0002 - Sections L/M
Amendment 0002 states that the Government will evaluate the lowest-priced offeror first and award if that offer is technically acceptable, but also states that the Contracting Officer may select a higher-priced quotation when it represents better value. Please confirm the controlling award method: sequential lowestprice technically acceptable evaluation or best-value tradeoff. A01: At the time of the question there was only one amendment to extend the period of performance. The basis of award will be best-value tradeoff.
Q02: SOO; Technical Exhibit 2
The SOO describes the work as approximately 204 rolling dips and associated lead-out ditches, while Technical Exhibit 2 establishes a final milestone of at least 204 accepted treatments. For proposal pricing, please confirm that 204 accepted rolling dips and associated lead-out ditches is the contractual quantity included in the required single all-inclusive price. If the Government designates a different quantity, please state how the scope and contract price will be adjusted.
A02: SOO Technical Exhibit 2: 204 accepted rolling dips and associated lead-out ditches is the contractual quantity included in the required single all-inclusive price
Q03: SOO - lead-out ditch requirements
The SOO states that lead-out ditches may extend up to approximately 57.5 feet from the road centerline and that exact lengths will be Government-flagged in the field. For proposal pricing, please provide the anticipated total or average linear footage of lead-out ditch excavation, or another quantity assumption offerors should use. Please also confirm whether 57.5 feet is the maximum length for any individual lead-out ditch. A03: SOO Lead out ditch requirements: Length assumption for lead-out ditches: roads are approximately 14 foot in width. Lead-out ditches will extend no more than 50 feet from the edge of the road (i.e. or no greater than 57.5 feet from the centerline of a road) . 57.5 from the centerline of each road is the maximum length of all lead-out ditches.

Q04: SOO §3.2

SOO §3.2 states that the Government will provide digital georeferenced maps in PDF or KML format. Please confirm whether those files will be available before proposal submission. A04: SOO 3.2: There are PDF and KMLs included in the contracting package Q05: Project road network / Technical Exhibit 4
May prospective offerors and proposed subcontractors independently access and inspect the project road