QnA CO OMAD 300 Minuteman Missile Access
Updated
A PDF document (104 KB) attached to CO OMAD 300(71) Minuteman Missile Access, from the Federal Highway Administration. Due Dec 2, 2026, 2:00 PM (UTC-7).
File name: QnA CO OMAD 300(71) Minuteman Missile Access 11.17.26.pdf
The full file is for paid members, or buy this bid alone.
Preview
6982AF27B000010
CO OMAD 300(71) Minuteman Missile Access
Question
Answer
1. Would it be possible to obtain any available
DWG/CAD drawings, project location maps,
or GIS files identifying the proposed roadway
segments and culvert locations?
KMZ files containing routes/culverts
separated out by Schedule have been
uploaded to sam.gov. Data and information
furnished is for the Contractor's information.
The Government is not responsible for any
interpretation of, or conclusion drawn from
the data or information by the Contractor.
November 12, 2026
Question
Answer
2. Will an amendment be posted, if so when?
Yes, please refer to sam.gov to check for
amendments.
It depends on when the amendment posts. If
there is a reasonable amount of time for the
contractor to incorporate changes from the
amendment into their bid, then the bid date
will hold.
3. Will the bid date be pushed out as a result
of the amendment?
4. Is there a public bid opening?
Yes, refer to Item 8 on page A-3. A public bid
opening will be held in person. There are no
options to attend virtually.
5. The project has priority numbers in the
summary table. Do you have to construct
them in order? Or can you complete all
culvert work first prior to surfacing?
UPDATE: No requirement to build in order of
the priority shown in the plans.
6. Can you work on multiple sites at the same
time?
Yes
7. SCR Section 156: Allowed road closures if
contractor signs a detour. Can only close road
10 am – 4 pm. Can you request a longer
period of time from CO to allow closure for a
longer window of time?
Yes, in accordance with SCR 156.06(l).
No restrictions on simultaneous work as long
as contract requirements are met and as
approved by CO.
6982AF27B000010
CO OMAD 300(71) Minuteman Missile Access
8. Culverts: At culverts, the contractor is
required to remove debris and vegetation.
Based on that, is the contractor required to do
soil and erosion control?
Yes, in accordance with FP-24 Section 157
Soil and Erosion Control.
November 16, 2026
Question
Answer
9. What kind of restrictions are there for this
job?
Please refer to SCR’s, especially Sections
107, 108, and 156.
10. Will there be gates/checkpoints? Security
clearance checks?
No
11. Do you have a preferred gravel source?
Contractor to provide material source in
accordance with plans and SCR’s.