Questions and Answers (002)
Updated
A Word document (24 KB) attached to GAOA Pine Creek Vault Toilet HTNF, from the Forest Service. Due Nov 5, 2026, 5:00 PM (UTC-8).
File name: C04 127EAX27Q0009 Questions and Answers 10-28-2026 (002).docx
The full file is for paid members, or buy this bid alone.
Preview
Please provide the CXT model, drawings, component weights, lifting requirements, and missing Section 133402. Is the vault single or double? The model is a Single Vault (as stated in the statement of work) Gunnison. All specifications and drawings are available at the manufacturer’s website.
Does Option 1001 include removing the underground vault and pumping/disposal of its contents? Please provide dimensions and any hazardous-material survey. Yes. All work is the responsibility of the contractor. No hazardous material survey exists. Contents are raw sewage.
What transport route is approved, and are there load/clearance restrictions or required road improvements? Contractor is free to determine best transport route. All are approved.
Which backfill, compaction, excavation protection, and testing requirements govern where Sections 133450 and 312000 conflict? Please also confirm the required field testing and frequency. This question will need to be more specific.
Are rock/groundwater records available, and is blasting prohibited? No exploratory excavation was performed. Blasting will not be permitted or necessary. What are the required dimensions and limits of the accessible path and surrounding aggregate? The path (to be constructed later) will meet the Architectural Barriers Act requirements, and will be the responsibility of the government (at a later date). Building corners will be set by the government. Finish grade shall meet existing per the drawings provided in this solicitation. What are the correct start/completion dates?
The start date is 7/15/2027, the contractor shall have 30 days from that date to complete the project. When may Option 1001 be exercised, and will demolition occur during the same mobilization and 30-day performance period as the base work? The option will be awarded at the same time as the base contract. The period of performance for the option will be within the same period of performance as the base.
Contractor's license: The technical proposal asks for proof of a current contractor's license. If the prime contractor uses a licensed Nevada subcontractor for the excavation and installation, is the subcontractor's license acceptable? That is acceptable. The licensed sub-contractor whose license is submitted in the technical proposal shall not be substituted/replaced in the execution of the work. Access: Are there any weight or length restrictions on the dirt road into Pine Creek Campground for a lowboy trailer and crane?