NATIONAL AERONAUTICS
AND SPACE ADMINISTRATION
Preparing Activity:
NASA
UFGS-21 22 00.00 40 (November 2023)
-----------------------------------Superseding
UFGS-21 22 00.00 40 (May 2016)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2023 **************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 21 - FIRE SUPPRESSION
SECTION 21 22 00.00 40
CLEAN AGENT FIRE EXTINGUISHING SYSTEMS
PART 1
GENERAL
1.1
REFERENCES
1.2
SUBMITTALS
1.3
QUALITY CONTROL
1.3.1
Special Hazards Suppression Systems
1.3.2
Previous Product Installation
PART 2
PRODUCTS
2.1
SYSTEM DESCRIPTION
2.1.1
Installation Drawings
2.1.2
Design Requirements
2.1.3
Equipment Approval
2.1.4
Performance Requirements
2.1.4.1
Time-Delay Occupied Spaces
2.2
EQUIPMENT
2.3
COMPONENTS
2.3.1
Piping
2.3.1.1
Pipe Hangers And Supports
2.3.1.2
Pipe Sleeves
2.3.2
Escutcheons
2.3.3
Supervisory Switch
2.3.3.1
Low Pressure Alarm Switch
2.3.4
Control Panel
2.3.4.1
Secondary Power Supply
2.3.4.1.1
Storage Batteries
2.3.4.1.2
Battery Charger
2.3.5
Manual Actuation Stations
2.3.6
Smoke Detectors
2.3.6.1
Air Sampling Detectors
2.3.6.2
Ionization Detectors
2.3.6.3
Photoelectric Detectors
SECTION 21 22 00.00 40
2.3.6.4
Detector Spacing and Location
2.3.7
Inhibit Switch
2.3.8
Alarm Signaling Devices
2.3.8.1
Audible Alarms
2.3.8.2
Visual Alarms
2.3.9
Main Annunciator
2.3.9.1
Annunciation Zones
2.3.9.2
Annunciator Panels
2.3.10
Automatic Fire-Smoke Dampers
2.3.11
Electromagnetic Door Holder Release
2.4
ACCESSORIES
2.4.1
Electrical Work
2.4.1.1
Wiring
2.4.1.2
Operating Power
2.4.1.3
Conductor Identification
PART 3
EXECUTION
3.1
INSTALLATION
3.1.1
Warning Signs
3.1.1.1
Inside Control Room
3.1.1.2
Protected Space
3.1.1.3
Manual Activation or Release Station
3.1.2
System Control
3.1.2.1
Controls
3.1.2.2
Suppression System Safing/Disconnect Switch
3.1.3
Electrical Work
3.1.4
Operating Instructions
3.1.5
Field Painting
3.2
FIELD QUALITY CONTROL
3.2.1
Manufacturer's Field Service
3.2.2
Test Procedure
3.2.3
Preliminary Tests
3.2.4
Formal Tests
3.3
CLOSEOUT ACTIVITIES
3.3.1
Record Drawings
-- End of Section Table of Contents --