Statement of Work APHIS VS Animal Import Center Miami
Updated
A PDF document (136 KB) attached to USDA APHIS Animal Import Center Miami - BAS Modernization, from the Animal and Plant Health Inspection Service. Due Nov 19, 2026, 3:00 PM (UTC-5).
File name: Statement of Work_ APHIS VS Animal Import Center Miami.pdf
The full file is for paid members, or buy this bid alone.
Preview
Statement of Work
EcoStruxure Building Operation Modernization
Project: EcoStruxure™ Building Operation Modernization
Client: USDA APHIS Veterinary Services (VS) Animal Import Center - Miami Address: 6300 NW 36th St. Miami FL 33122
1.0 Scope of Work
The Contractor shall furnish all necessary labor, equipment, materials, supervision, programming, and technical services to modernize the existing Building Automation System (BAS) at the USDA APHIS VS Animal Import Center located in Miami, Florida. The modernization shall include removal and replacement of obsolete controllers, installation and configuration of compatible replacement equipment, integration with the existing system, programming, graphics development, testing, commissioning, and personnel training. The Contractor shall retain and reuse functioning control panels, wiring, and field-level equipment where specified in this Statement of Work.
2.0 Background
The Miami Animal Import Center utilizes an existing Building Automation System to monitor and control HVAC equipment supporting facility operations, including animal quarantine areas. Several existing controllers are obsolete and no longer supported by the manufacturer. Modernization is required to restore reliable system communication and centralized monitoring while maintaining compatibility with functioning infrastructure.
3.0 Technical Requirements
3.1 Building Management System Automation Server
The Contractor shall furnish and install one (1) Schneider Electric EcoStruxure Building Operation AS-P Automation Server to replace the existing CMX 9924 network controller. The Contractor shall: Decommission and remove the existing CMX 9924 controller. Install the replacement AS-P within the existing building management system panel or an appropriate enclosure, as required. Connect the replacement server to the Ethernet network. Configure centralized control and supervision of the replacement chiller and air-handling-unit controllers. Establish and verify communication with retained field-level controllers, including applicable VAV controllers. Configure system graphics, alarms, trends, setpoints, schedules, and web-enabled access.
3.2 Chiller Plant Controller Replacement
Statement of Work
EcoStruxure Building Operation Modernization
The Contractor shall furnish and install one (1) Schneider Electric SpaceLogic EBO MP-C controller to replace the existing SCX 920 chiller plant controller. The Contractor shall: Decommission and remove the existing SCX 920 controller. Identify,