SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS

D.1 – STATEMENT OF WORK

CONTRACT TITLE: Tri-Annual PM & Testing for Substations and Switch Gears

PLACE OF PERFORMANCES: VA San Diego Healthcare System, 3350 La Jolla Village Dr., San Diego, CA 92161

PERIOD OF PERFORMANCE: Base year – December 7, 2026 – December 6, 2027

CONTRACT TYPE: Firm Fixed Price

BACKGROUND: In accordance with the requirements of VHA Directive 1028 and the Joint Commission Standard 7.40 EP 5, electrical equipment is inspected, tested, maintained and/or calibrated every 36 months, and all work must be documented. A test of the Essential Electrical System (EES) that lasts 4 hours continuously should be planned and executed every 36 months in accordance with the requirements of NFPA 70B, NFPA 99, NFPA 110 and NETA, will be conducted at the same time to support this 8-to-10-hour event.

GENERAL REQUIREMENTS:

The contractor will:
Provide maintenance and testing of the electrical distribution system at VA San Diego Medical Center for the following buildings:

Bldg. 2, Main Switchgear, Ground Level Room 102
One (1) Medium Voltage Switch
Five (5) 15 kV VCP – W Circuit breakers
Fifteen (15) Protective Relays 50/51
Two (2) Protective Relays SEL 351

Bldg. 11 Substation K, Room BA112
Two (2) Medium Voltage Switches
One (1) 12000/480-277, 750 kVA, OA Transformer
One (1) LV Switchboard with 12 molded breakers
One (1) Main Breaker
Nine (9) sections consisting of bus, insulators, current transformers, potential transformers controls and wiring One (1) 15 kV incoming substation switchgear

Bldg. 2 Cogen Switchgear, Generator Substation Area
Three (3) Medium Voltage Siemens circuit breakers
Two (2) potential transformer cabinets
Four (4) sections consisting of bus, insulators, current transformers, potential transformers controls and wiring

One (1) SEL 300G

One (1) switchgear
Two (2) Protective Relays SEL 735

Bldg. 27
One (1) Pad mount transformer 12kV/480V
One (1) 1200 AMP Main Breaker, molded case
Two (2) sections of bus, insulators, current transformers, potential transformers controls, and control wiring One (1) main breaker, molded case
One (1) LV switchboard

Bldg. 28 Parking Garage
One (1) Pad mounted transformer 12 kV-480V
One (1) LV switchboard
One (1) 400 AMP main breaker, molded case
One (1) Automatic transfer Switch

Scope of Work
This section outlines the proposed scope of work for electrical equipment maintenance and testing services for VASDHS.