Home / 460-26-004 | Wilmington VAMC Roof Replacement | NCO 4… / Document

Statement of Work Roof Replacement 3D PT Roof 10 Roof 11 updated 01

Updated

A PDF document (151 KB) attached to 460-26-004 | Wilmington VAMC Roof Replacement | NCO 4 Construction East (VA-26-00029152), from the Department of Veterans Affairs. Due Nov 4, 2026, 11:00 AM (UTC-5).

File name: SOW Roof Replacement 3D PT Roof 10 Roof 11 updated 01.pdf

Download the full documentSee the bid

The full file is for paid members, or buy this bid alone.

Preview

VAMC Wilmington, DE

Roof Replacement 3D, PT,10, and 11

Wilmington, DE VA Medical Center
Wilmington, DE 19805

SCOPE OF WORK

For

Replace Roof 3D, Physical Therapy Roof, Roof 10, Roof 11 Project No.
-- Services -Provide:
• Professional construction services to include but not limited to: a.
Site investigation
b.

Construction to be performed- Remove and replace Roof 3D, Physical Therapy Roof, Roof 10, Roof 11
-- Project Scope --

GENERAL:

• VA Medical Center Wilmington intends to issue a construction contract. The project consists of: a. The Contractor shall provide all labor, transportation, materials, equipment, and supervision required to perform the removal and replacement of roof 3D, PT Roof, Roof 10, Roof 11 at the Wilmington VA Healthcare System, located at 1601 Kirkwood HWY, Wilmington, Delaware 19805.
b. See attachment for roof locations

SPECIFICS:

•

Building 1, Roof 3D, PT Roof, Roof 10, and Roof 11
a. Demo and remove all roofing material and insulation below the membrane to fully expose the decking.
b. Dispose of all demoed material properly in accordance with 01 74 19 Construction Waste Management. Contractor must provide own dumpsters if needed c.

Prep steel decking and brick walls to receive new tapered insulation and roofing membrane. This also means to fill any voids/roof curbs that are no longer in use from penetrations.

d. Remove any items that are no longer in use. Coordinate with COR for said items. e. Repair all roof drains and make it to the original interior diameter. Insertable retrofit drains are unacceptable.
f.

Roofs shall slope to the drain to where there will be no puddled water after a rain fall.

g. 60 Mil. Elevate RubberGard™ EPDM LS-FR Low-Slope Fire Retardant white roofing material or equivalent, flat tapered insulation, HD cover board, or equivalent h. All other materials as required

VAMC Wilmington, DE

•
•

Roof Replacement 3D, PT,10, and 11

i.

Install new pipe collars and pipe flashing around existing pipe penetrations.

j.

Install must meet high wind zone design requirements.

k.

All parts involved with the roofs weather tight integrity shall be warrantied against leaks for a minimum of 20 years.

l.

All areas that are affected by this project will have a before construction, during construction and after construction picture taken.

Work to be scheduled to interfere as little as possible with normal VA operations. Contractor responsible for patching and sealing all penetrations. Finish matching existing. In some instances, this may require painting corner to corner to prevent obvious patchwork.

The beginning of the document. Download the full file to read on.

Other documents in this bid