SOW, SR EMBEDDED FLOOR PLATES

RELEASE DATE : 2026-10-06

Officially Released To the LBNL Document Control Center Released: October 6th, 2026 DCC Auth Key: Z6DBTZ9DSK

AUTHOR:

DOCUMENT NUMBER: AL-1953-0482

DOCUMENT STATUS: RELEASED

DOCUMENT TYPE: REQUIREMENT

CATEGORY CODE: AL7525

Downloaded by: Jessica Nicole Aguilar at October 06, 2026 15:23:46

REVISION: C

AL-1953-0482 REV.C

Doc.Status:RELEASED

REVISION HISTORY​

APPROVALS​

Abbreviations and Acronyms​

1 Introduction​

1.1 Project Overview​

1.2 Description of Items​

1.3 Roles and Responsibilities​

2 Scope of Work​

2.1 Work required​

2.2 Optional value-added services​

3 Deliverables and Schedule​

3.1 Deliverables: Hardware​

3.2 Deliverables: Quality assurance documentation​

3.3 Options​

3.3.1 Option 1: Storage and controlled materials release​ 3.3.2 Options 2 & 3: Post completion additional machining​

4 Project Administration​

4.1 Reporting/Communication Requirements​

4.2 Reviews and Approvals​

4.2.1 Manufacturing readiness review​

4.2.2 Pre-shipment documentation review​

4.2.3 Machining option review​

4.3 Hold Points​

4.4 Documentation Management​

5 Packaging, Storage, and Shipping Requirements​

5.1 Packaging​

5.2 Storage​

6 Quality Assurance​

6.1 Quality Reporting Requirements​

Officially Released To the LBNL Document Control Center Released: October 6th, 2026 DCC Auth Key: Z6DBTZ9DSK

6.1.1 Deviation requests​

6.1.2 Nonconformance reports​

6.2 Inspection Requirements​

6.2.1 Work Package 1​

6.2.2 Acceptance Criteria​

7 Applicable Documents​

Advanced Light Source

Lawrence Berkeley National Laboratory

All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages Printed hard copies of this document are for reference only.

Downloaded by: Jessica Nicole Aguilar at October 06, 2026 15:23:46

Officially Released To the LBNL Document Control Center Released: October 6th, 2026 DCC Auth Key: Z6DBTZ9DSK

AL-1953-0482 REV.C

Doc.Status:RELEASED

Advanced Light Source

Lawrence Berkeley National Laboratory

All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages Printed hard copies of this document are for reference only.

Downloaded by: Jessica Nicole Aguilar at October 06, 2026 15:23:46

AL-1953-0482 REV.C

Doc.Status:RELEASED

REVISION HISTORY

Rev.

CM Number

A

Description of Change
Baseline Release

APPROVALS

The following individual(s) shall review this document: Reviewer