Home / Reserve Basin Maintenance Dredging Contract for Sites at… / Document

Amendment 3: Rev Specifications Section 01 45 00

Updated

A PDF document (89 KB) attached to Reserve Basin Maintenance Dredging Contract for Sites at the Phildelphia Navy Yard in the Public Works Department Pennsylvania Area of Responsibiliy, from the Department of the Navy. Due Jan 15, 2027, 2:00 PM (UTC-5).

File name: AMEND0003 Rev Spec Section 01 45 00.pdf

Download the full documentSee the bid

The full file is for paid members, or buy this bid alone.

Preview

PNY Reserve Basin FY26 Maintenence Dredging

1783178

SECTION 01 45 00

Revised 08-11-2026

QUALITY CONTROL

08/23, CHG 2: 05/25

PART 1

1.1

GENERAL

REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C1077

(2024) Standard Practice for Agencies
Testing Concrete and Concrete Aggregates
for Use in Construction and Criteria for
Testing Agency Evaluation

ASTM D3666

(2016) Standard Specification for Minimum
Requirements for Agencies Testing and
Inspecting Road and Paving Materials

ASTM D3740

(2019) Minimum Requirements for Agencies
Engaged in the Testing and/or Inspection
of Soil and Rock as Used in Engineering
Design and Construction

ASTM E329

(2023) Standard Specification for Agencies
Engaged in Construction Inspection,
Testing, or Special Inspection

ASTM E543

(2021) Standard Specification for Agencies
Performing Non-Destructive Testing

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1

1.2

(2024) Safety -- Safety and Occupational
Health (SOH) Requirements

PAYMENT

Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Schedule item.
1.3

SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan; G

SECTION 01 45 00

PNY Reserve Basin FY26 Maintenence Dredging

1.4

1783178

GENERAL REQUIREMENTS

Establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction. QC is comprised of plans, procedures, and organization necessary to produce an end product that complies with the Contract requirements. The QC system covers all construction operations, both onsite and offsite, and must be keyed to the proposed construction sequence. The Quality Control Manager, Superintendent, Site Safety and Health Officer (SSHO), and all on-site supervisors are responsible for the quality of work and are subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the Contract. The Quality Control Manager must maintain a physical presence at the work site at all times and is the

The beginning of the document. Download the full file to read on.

Other documents in this bid