1.

General Description of Works

The project is to provide a feasibility report, then based upon the output of the report, an approved 100% design and firm price construction cost sufficient to complete all preconstruction engineering designs, managing site clearances, installing the pad foundation network, and delivering fully commissioned utility connections up to the building’s internal termination points.
2.

Requirements

Project Objective
The objective of this contract is to provide all pre-construction engineering, design, site preparation, substructure installation, and utility servicing required to fully facilitate the installation of a new, single storey modular building. Upon completion, the structure will function as a community hub housing a library and café.
The completed works must be fully compliant, structurally sound, fit for purpose, and ready for immediate modular building installation.
Pre-Construction, Design & Survey Requirements
• Complete all comprehensive topographical, boundary, and level surveys required to establish definitive datum points and dimensional accuracy for the modular building footprint.
• Execute all necessary intrusive and non-intrusive ground investigations including dynamic sampling, borehole testing, and trial pits, to produce a conclusive geotechnical report for the foundation design.
• Conduct all necessary soil sampling and Waste Acceptance Criteria (WAC) testing to accurately classify, manage, and legally dispose of all surplus excavated materials off site. • Perform a comprehensive buried services trace, utility mapping exercise, and CCTV drainage connectivity survey to verify the exact location, condition, and capacity of all existing infrastructure.
• Procure all mandatory statutory utility records and secure all necessary technical approvals prior to the commencement of physical works.
• Produce a detail, and sign off on all comprehensive structural substructure designs, pad foundation layouts, and gravity fed drainage networks.
Earthworks & Sub-Base Engineering
• The Contractor is responsible for verifying all subsurface conditions and executing all earthworks required to achieve the necessary structural bearing capacity and final design levels.
• Strip and segregate all topsoil across the works footprint to a depth determined by the site investigations as necessary to reach a clean, load bearing subgrade. • Execute all bulk excavations to the definitive depths required to achieve the final design