Attachment 2: Statement of Work and Specifications
Updated
A PDF document (404 KB) attached to Green Mountain National Forest Storage tank cleaning and inspection at Hapgood Pond, from the Forest Service. Due Nov 2, 2026, 12:00 PM (UTC-5).
File name: C05 Attachment 2- Statement of Work and Specifications .pdf
The full file is for paid members, or buy this bid alone.
Preview
HAPGOOD POND RECREATION AREA
WATER TANK REHABILITATION
TECHNICAL SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01100 - SUMMARY OF WORK
01200 - MEASUREMENT & PAYMENT
01350 – PROJECT MANAGEMENT AND COORDINATION
DIVISION 22 – PLUMBING
22120 – WATER STORAGE TANK REHABILITATION
END OF INDEX
SECTION 01100
SUMMARY OF WORK
PART 1 - GENERAL
1.01
PROJECT IDENTIFICATION
Project Name and Location: Hapgood Pond Recreation Area Water Tank Rehabilitation. Located on Hapgood Pond Road, Town of Peru, Bennington County, VT. 1.02
A.
SUMMARY OF WORK
Project Summary Description: The project includes, but is not limited to, the following major items of Work:
1. Water storage tank – Remove all sediment and pressure wash inside and out, seal holes and cracks, coat entire interior and exposed exterior of tank with cementitious coating, sanitize tank. Water tank interior dimensions are approximately 15’-4” diameter and 8’-9” deep.
1.03
SCHEDULE OF GOVERNMENT-FURNISHED PROPERTY
A. Government furnished property to be installed by the Contractor:
1. None
1.04
MISCELLANEOUS PROVISIONS
A. The Contractor shall comply with the requirements of all permits obtained by the Government. The Contractor is responsible to pay for all inspection fees related to permits or requirements of other governing agencies, utilities, etc.
END OF SECTION
SECTION 01200
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.01
SUMMARY
A. This Section includes:
1. Measurement and payment criteria applicable to the work performed under a Lump Sum payment method.
2. Defect assessment and non-payment for rejected work.
1.02
AUTHORITY
A. The Contracting Officer’s Representative (COR) will take all measurements and compute quantities accordingly.
1.03
MEASUREMENT OF QUANTITIES
A. Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the Contract, including all necessary materials, equipment, and labor to complete the job. They will not be measured.
1.04
PAYMENT
A. Payment Includes: Full compensation for all required labor, products, tools, equipment, plant, transportation, services, and incidentals; erection, application, or installation of an item of the Work; overhead and profit.
1. "Incidentals" are to be considered as an additional obligation to the other work required for the item(s). Incidental work is not payable directly, but is to be considered included in the contract price for the item(s) of work specified. 2. All work not specifically identified as a separate bid item in Subsection 1.05 below is