General Services Administration
Nevada Field Office

Scope of Work
FHWA Carson Office Renovation
Carson City, NV

9/28/26

DEV 12-1-2014

General Services Administration
Nevada Field Office
333 Las Vegas Blvd South
Las Vegas, Nevada 89101

STATEMENT OF WORK

9/28/26
Project Title:
1.0
Description
The Federal Highway office in Carson City requires several modifications and upgrades to office 225 and office wide systems. Scope of work includes the following: 1. Demo and reconstruct STC-45 sound rated wall around office 225. New wall must take into account alteratations, to floor finishes, suspended ceiling, and asbestos testing. New wall shall include sound rated door and door frame.
2. Remove and re-Install all roller shades throughout office. Replace four roller shades. New roller shades shall match existing as closely as possible. Specifications are included in SOW addendum.
3. Mount Video Teleconferece System in Office 225
4. Install sound masking system throughout office.
2.0
General
Provide all supervision, labor material and equipment required to complete scope of work.
All dimensions are approximate and may vary from actual measurements. It is the contractor’s sole responsibility to field verify all measurements, site conditions, utility/service locations and equipment/material compatibility. 3.0
Contractors Cost Proposal
The contractor shall provide a detailed proposal showing material and labor cost for each line item. The proposal shall include but not limited to Labor Burden, Contractor Profit, Contractor Overhead, Insurance and Bond Rate.

5.0 Performance Period

Project must be completed no later than 60 calendar days after a notice to proceed has been issued.

6.0 Submittals

Prior to the purchase of any materials, the contractor is to provide product design, layout drawings, material submittals (3 copies), and specific technical information for review and acceptance on the following items:
➢ Roller Shades
➢ Sound Mask System
8.0

Schedules/Deliverables

DEV 12-1-2014

Agency Initial
Date

General Services Administration
Nevada Field Office
333 Las Vegas Blvd South
Las Vegas, Nevada 89101

Contractor shall provide a construction schedule to the GSA Project Manger within 3 working days after receipt of notice to proceed. Contractor shall provide written weekly updates of the schedule to the GSA Project Manager. Contractor shall provide copies of material orders with tracking numbers to the GSA Project Manager on all lead items.