Section C – Attachment 4
List of Deliverables
22 OCT 2026
Amendment Four (A00004)
RECORD OF CONTRACT CHANGES
Version
Orig.
Date
09/30/2026
A00004
10/22/2026
70Z02326R93250001
Purpose
Request for Proposal (RFP)
A00004 incorporates the following revisions:
1) Added the Coversheet and Record of Contract
Changes.
2) Updated the far-right column description from
“Pricing Sheet” to “Pricing Schedule / CLIN.”
3) Deliverable 14: Revised to reference 068-1.4
from 068-1.3.
4) Deliverables 23 and 24: Revised to reference
083-6 from 083-7.
5) Deliverable 40: Designated as "Reserved" to
align with SOW Section 091 being reserved.
The testing requirements for both the first boat
(demonstrator) and follow-on boats have been
consolidated and clarified within the revised
SOW Section 092.
6) Deliverables 41 & 42: Revised to reference
the updated SOW section numbers.
7) Deliverables 43 & 44: Revised to reference
the updated SOW section numbers and added
a requirement for hard-copy documentation to
be delivered with the boats.
8) Deliverable 45: Revised to require hard-copy
documentation to be delivered with the boats.
9) Deliverable 52: Revised to reference 660-1.1.6
from 660-1.1.5.
10) Deliverables 54 & 55: Added to establish
requirements for first boat acceptance testing
and documentation.
Response Boat -Small Third Generation (RB-S III)
Section C Attachment 4 List of Deliverable A00004
RB-S III
List of Deliverables
#
SOW / SPEC Ref.
Deliverable Description
Milestone
To
Required Delivery
N/A
Contract Award
KO &
COR
At Award
040-2.1.2
040-2.4
Offeror Proposal – Volume I
– Technical Proposal
including all appendices
Formal Meeting Agenda
• Post Award Conference
• Open Hull Inspection
KO &
COR
Formal meeting agenda
seven days prior to the
formal meeting
X001
• Post Award Conference
• Open Hull Inspection
• Acceptance Testing
• Post-Operational Test and Evaluation
Review.
• Follow-On Order Year Reviews
Post Award Conference
KO &
COR
Formal meeting minutes two
days after conclusion of the
formal meeting
X001
KO &
COR
X001
Starting with acceptance of second boat
KO &
COR
Monthly for the first 12
months; Quarterly thereafter,
at the end of March, June,
September, and December
• With the boat
• As needed with change(s)
The beginning of the document. Download the full file to read on.