P1550 PPI RESPONSES 6
Updated
A PDF document (163 KB) attached to Design-Bid-Build (DBB) SOF Marine Raider Facilities Complex, Marine Corps Base (MCB) Camp Lejeune, North Carolina, from the Department of the Navy. Due Oct 30, 2026, 2:00 PM (UTC-4).
File name: P1550 PPI RESPONSES 6.pdf
The full file is for paid members, or buy this bid alone.
Preview
PPI
#
Date
Submitted
10/19/2026
Reference
Page
Section
Paragrap
h
Question
Response
The RFP design and specifications for the S&C Vista switch (Drawing ES 504) is available from only one vendor, which makes this equipment a sole-source piece of equipment.
The specific manufacturer and model name identified on the contract drawing (ES 504) represents the basis of design only to establish the required form, fit, function, and salient performance characteristics. A sole source brand name requirement does not apply, and thus no need for a Justification and Approval. In accordance with FAR 52.236-5(a), any brand name reference on contract drawings is legally interpreted as including "or equal," allowing open competition among technically compliant
manufacturers without necessitating a drawing redraw or preaward amendment. Contractors may propose any manufacturer's equipment that meets or exceeds the requirements detailed in the contract specifications and drawings.
Quantity of CLIN 0001I has been adjusted. Option 2 modified to account for soil disposal. Please see revised Price Proposal Form provided with Amendment 0013
The solicitation does not include a Justification and Approval document for the sole source item. We request NAVFAC provide the legally required Justification and Approval document, or in the absence of justification, issue a modification to the solicitation to remove the unjustified sole source equipment.
10/19/2026
10/19/2026
PPI #23 states the 70,000 tons is an engineering estimate for the amount of surplus soils created for the entire project (the implied maximum amount of soils generated from construction). The Subcontractors we have spoken with are providing a range of their own estimates that vary from 130,000 to 170,000 T of surplus soil. This indeterminate range represents some risk to the GC and the Navy. PPI #23 response further indicates that ALL surplus soil will have to be hauled to a RCRA D facility (the implication that ALL project surplus soil is contaminated). Please confirm that bidders are to assume all project surplus soil is to be hauled offsite to a RCRA D facility. Or alternately should this CLIN 001 I be an OPTIONAL CLIN with indefinite quantity of contaminated soil - unit price per ton against a quantity above 70,000 T? Non-contaminated surplus soils could be disposed of off base (locally).
FYI- The estimated cost for this testing and hauling to such a RCRA D facility are upwards of $200/ T making the additional cost > $20M
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Bid document
- SPC
- Attachment B - PIEE Vendor Access Instructions
- Attachment C - Price Proposal Form
- Attachment D - Construction and Design Experience Project Data Sheet
- Attachment E - Past Performance Questionnaire
- Attachment F - Historical Small Business Utilization
- Attachment G - SPCD
- Attachment H -Small Business Subcontracting Plan
- Solicitation
- Amendment 1
- Attachment C - Price Proposal Form Revised