25 Sep 2020 Questions and Answers
1. Questions: On page 3 of the draft RFP, Part I Section B states: “The single proposal shall differentiate between the Groups so that the proposal includes a Section A for Group A, Section B for Group B, and Section C for Group C. Offerors are reminded that the Government will only evaluate one (1) proposal from each offeror.” Our assumption is that relevant past performance would be the same for all three Groups and offerors are simply identifying the Group(s) they want to be considered for award in Volume I of proposal.
Please Clarify:
a. Question: How should an offeror differentiate between Sections/Group? Answer: The offeror will differentiate by identifying the Groups which are separated by CLINs. The Preamble of the RFP indicates the specific CLINs for each group. There is also a preamble for each separate group. The offeror’s proposal will identify (in the cover letter) which Group [Group A (CLINs X001-X131), or Group B (CLINs X132X385), or Group C (CLINs X386-X437)] or any combination of each Group by identifying the group and CLINs.
b. Question: What is the submission requirement for each Section/Group? Answer: The submission requirement is to identify the group or groups the offeror is proposing. The quantities and prices are to be determined at order level so the only requirement is to identify the group. The proposal requirements are detailed in Section L and the RFP’s Preamble. Identify the Group [Group A (CLINs X001-X131), or Group B (CLINs X132-X385), or Group C (CLINs X386-X437)] or any combination of each Group by identifying the group name and CLINs. The Government will clarify this submission requirement in the RFP Preamble.
2. Question: RFP Attachment 1, L-900, Section C - Volume 2, Para 2 – Past Performance states “Commercial contracts will not be considered as a part of this evaluation”. However, in RFP Attachment 4 Instructions for PPI, Page 17 paragraph 15 states “For commercial contracts provide points of contact fulfilling these same roles, if available.” Answer: The reference to the commercial customers via PPI is incorrect and will be removed. 3. Question: Are you able to share if the posting on the 18th confirms the due date response? We are seeking to provide a response and it’s unclear if the due date is 9-11 or a later date? Are we late to this?
Answer: The response date will be updated and reflected in the PreSolicitation notice on beta.SAM.gov. The response date will be 30 days after the release of the formal RFP. Currently
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Draft Request for Proposals ATTACHMENTS 1 and 4 through 8
- Draft Request for Proposals Attachment 3 Volume I Oral Presentations for Discussions Slide Deck
- Draft Request for Proposals Attachment 9 Volume II Oral Presentations for Discussions Slide Deck
- Draft Statement of Work
- Draft Request for Proposals
- Request for Proposals Attachment 2 Section M-900
- QandAs
- SRC Questions and Answers Posted to beta.SAM
- Questions and Answers
- Attachment 2
- Attachment 4
- Attachment 5