Date: 11/16/2026
SUBJECT: Summary of Changes, Amendment 0001, Asphalt
Contractor Questions
Closures and work hours: The SOW calls for strategic closures with minimal effect on daily operations and allows work outside normal business hours with Forest Service approval. Would a full closure of each lot on a weekend (for example, Friday evening through Monday morning) be acceptable at the Boulder, Clear Creek and Fort Collins sites? If not, should offerors plan on phased weekday work with part of each lot kept open? Forest Service Response Forest Service Response:
The offices will still need parking available, so a hybrid /phased work closure would be required
Contractor Question:
Site name: The Schedule of Items lists "Canyon Lakes Administrative Site," while the SOW and site maps list the "Fort Collins Administrative Site" at 300 South Hemlock. Please confirm these are the same location.
Forest Service Response:
The site should be referred to as “Fort Collins Administrative Site”.
Contractor Question:
Wage determination: The solicitation includes the Construction Wage Rate Requirements clauses, but no wage determination is attached. Please provide the applicable wage determination(s) for Boulder, Clear Creek and Larimer Counties.
Forest Service Response:
See Attachment 6 C)^ Wager Determination CO202600002.
Contractor Question:
Please see (Page limit: Section 52.212-1 states quotes shall be no more than 3 pages, not including the Schedule of Items, and also refers to a 10 page document criterion. Please confirm the page limit for the technical approach narrative, and whether the construction schedule (Gantt chart) counts toward it.
Forest Service Response:
Page document Criterion will reflect 3 pages and not 10 for the Technical Approach
Contractor Question:
It requires a asphaltic oil emulsion material. It is usually a Type I or Type II slurry seal. While this is technically a sealer, it is designed for high traffic areas like highways or streets. A parking lot doesn't have enough rolling traffic to knead the sealer with vehicular traffic. These materials, being asphaltic oil derivative don't have the true impervious characteristics of a Coal Tar sealer blended with 20% asphaltic oil such as your spec indicates. Coal tar blends are designed for lower traffic areas such as parking lots. They are impervious to anything that leaks out of vehicles and non-porous meaning that they won't absorb water like asphalt emulsions. The idea of a true sealer is to keep moisture from the asphalt under it. They can be installed as a slurry just as the one spec-ed. The difference is that they use a smaller aggregate mixed in a heavier concentration in the seal material. Usually about 4 Lbs. per gallon and are installed with an 8' wide brush and squeegee machine. These won't delaminate from water absorption like the asphalt-based emulsions