Home / 620-26-206 Asbestos Abatement / Document

Specifications Project 620-26-206 General Requirements

Updated

A PDF document (176 KB) attached to 620-26-206 Asbestos Abatement, from the Department of Veterans Affairs. Due Nov 20, 2026, 1:00 PM (UTC-5).

File name: Specs _ Project 620-26-206 _ General Requirements.pdf

Download the full documentSee the bid

The full file is for paid members, or buy this bid alone.

Preview

Va Medical center Montrose
Abate Asbestos in building
3Pt/ sleep study

VA Project No. 620-26-206
8/12/2026
100% submission

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and

infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations,

including demolition and removal of existing structures, and

furnish labor and materials and perform work for the abatement of Building 3PT/Sleep study as required by drawings and
specifications.

B. Visits to the site by Bidders may be made only by appointment

with the Medical Center Engineering Officer

C. All employees of general contractor and subcontractors shall

comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID Work includes demolition

and abatement of asbestos hazards, necessary removal of existing structures and construction and certain other items.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website

where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative

security procedures that will remain effective for the entire duration of the project.

01 00 00 -1

Va Medical center Montrose
VA Project No. 620-26-206
Abate Asbestos in building
8/12/2026
3Pt/ sleep study
100% submission
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project

site without appropriate badge.

They may also be subject to

inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one

week’s notice to the Contracting Officer so that security arrangements can be provided for the employees.

This notice

is separate from any notices required for utility shutdown

described later in this section.

3. No photography of VA premises is allowed without written

permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project

The beginning of the document. Download the full file to read on.