SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
JB Charleston (Dec 2021)
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Resume for the proposed Superintendent; G
Preconstruction Survey; FIO
SD-04 Samples
Color Boards; G
SD-07 Certificates
Progress and Completion Pictures; FIO
1.2 COLOR BOARDS FOR AIR FORCE PROJECTS
[IF REQUIRED] Submit three sets of color boards within 90 calendar days after Contract Award for Design/Bid/Build construction contracts and no later than the 95% Design Submittal for Design/Build contracts. Each set of boards shall include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Samples shall be presented on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Modules shall be designed to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, samples not less than 12 inches square shall be submitted with the board. If more space is needed, more than one board per set may be submitted. The Contractor shall certify that he has reviewed the color samples in detail and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples shall not relieve the Contractor of the responsibility to submit samples required elsewhere herein.
1.3 PRECONSTRUCTION SURVEY AND PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Submit these photographs with a narrative report indicating the existing conditions of the project site prior to mobilization.
Provide monthly, and within one month of the completion of work, digital photographs, 1600 x 1200 x 24 bit true color 5-megapixel minimum resolution in jpeg file format showing the sequence and progress of work.
Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer’s Representative. Submit a view location sketch indicating points of view upon request.
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Solicitation
- Solicitation Attachment XU - Past Performance Customer Questionnaire
- Solicitation Attachment XV - Past Performance Survey
- Solicitation Attachment XW - JB Charleston MACC Work Load Estimate
- Solicitation Attachment XX - Task Order Proposal Request Seed Project
- Solicitation Attachment XY - On and Off-Ramp Procedures
- Statement of Work - JB CHS MACC
- Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A E)
- Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS Request for Information Form
- Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form (Submittal Register)
- Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form (Request for Information Register)
- Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures