Statement of Work - Attachment 8 - 01 32 00 - Project Schedule
Updated
A Word document (73 KB) attached to JB Charleston Multiple Award Construction Contract, from the Department of the Air Force. Due Nov 2, 2026, 12:00 PM (UTC-5).
File name: Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx
The full file is for paid members, or buy this bid alone.
Preview
SECTION 01 32 00 PROJECT SCHEDULE
JB Charleston (Dec 2021)
PART 1GENERAL
SUBMITTALS
Government approval is required for submittals with a "G" classification. Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Project Scheduler Qualifications; G Baseline Cost Loaded Critical Path Method (CPM) Project Schedule; G Schedule and Pay Request Calendar; G
SD-07 Certificates
Monthly Cost Loaded CPM Project Schedule Updates; G
SD-11 Closeout Submittals
As-Built Schedule; G
PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 5-years’ experience scheduling construction projects similar in size and nature, as identified in Section 01 11 00, to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application. A resume outlining the individual’s qualifications shall be submitted for acceptance by the Contracting Officer.
PART 2PRODUCTS
SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available.
Primavera
If Primavera P6 is selected for use, provide the P6 "xer" export file. Additionally, provide an exported .pdf files for submittal review IAW the “Schedule Reports” paragraph.
PART 3EXECUTION
GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in the development of the schedule and coordinate closely with the Contracting Officer, Contracting Officer's Representative, and Facility Manager(s) in its maintenance. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Solicitation
- Solicitation Attachment XU - Past Performance Customer Questionnaire
- Solicitation Attachment XV - Past Performance Survey
- Solicitation Attachment XW - JB Charleston MACC Work Load Estimate
- Solicitation Attachment XX - Task Order Proposal Request Seed Project
- Solicitation Attachment XY - On and Off-Ramp Procedures
- Statement of Work - JB CHS MACC
- Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A E)
- Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS Request for Information Form
- Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form (Submittal Register)
- Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form (Request for Information Register)
- Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures