KAUTZ Road Substation Construcion, UIP Subproject 2- KRS
Updated
Solicitation from the Department of Energy, for work in Batavia, Illinois. Due Dec 18, 2026, 4:00 PM (UTC-6), 45 days left.
| Title as posted | KAUTZ ROAD SUBSTATION CONSTRUCION, UIP SUBPROJECT 2- KRS |
|---|---|
| Solicitation number | RFP-383167-CD |
| Agency | Department of Energy |
| Office | Fermilab - Doe Contractor |
| Notice type | Solicitation |
| Set-aside | None |
| Trade (NAICS) | Power and Communication Line and Related Structures Construction (237130) |
| Product or service code | Z2MZ |
| Place of performance | Batavia, Illinois |
| Posted | Nov 2, 2026 |
| Response deadline | Dec 18, 2026, 4:00 PM (UTC-6) (45 days left) |
| Add the deadline to | Google Calendar · Apple / Outlook (.ics) |
Bid documents (18)
- Request for Proposals 1.0 Request for Proposals Instructions to Offerors 330 KB
- Exhibit A- Scope of Work- UIP Subproject 2 KRS 321 KB
- Exhibit B- Construction Drawing Set 72.2 MB
- Exhibit C- Specification Set 11.6 MB
- Exhibit D- FFDG General Terms and Conditions for Construction (10.2026) 303 KB
- Exhibit E - Construction Insurance Requirements 245 KB
- Exhibit F - Statement of Acknowledgment 699 KB
- Exhibit G - Fermilab Subcontractor Safety Information Questionnaire 1.4 MB
- Exhibit H- Price Proposal Form 469 KB
- Exhibit I- SARC Subcontractor Annual RepsCerts 471 KB
- Exhibit J- Proposal Cerftifications Form r5 406 KB
- Exhibit K Bond Bid 749 KB
- Exhibit L (Rev 1.25) - Payment Bond 1.6 MB
- Exhibit M Performance Bond 743 KB
- Exhibit N- Davis Bacon Wage Rater 1.4 MB
- Exhibit O- Small Business Subcontracting Plan Template 517 KB
- Exhibit P- Compliance With Federal Anti-Discrimination Laws- PRC EXH 469 278 KB
- Exhibit Q- Sample Firm-Fixed-Price Subcontract 747 KB
Paid members download every document from this page, or buy this bid alone.
Federal prevailing wage rates for this place: Illinois Davis-Bacon and SCA wage determinations.
Description
This scope of work is to rebuild and renovate the Kautz Road Substation (KRS), which is UIP subproject SP-2. The KRS supplies electricity to various lab buildings and systems. These systems serve both conventional facility needs, as well as process utility requirements.
It is vital to Fermilab’s mission that KRS be revitalized and expanded, ensuring the ability to serve existing and future loads. The General contractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings, technical specification and the detailed description contained herein.
The critical schedule constraint for construction of this project is Fermilab’s accelerator shutdown, with an anticipated scheduled start on January 1, 2028, and anticipated end date of January 1, 2030- these dates may change depending on the needs of the Lab. The General Contractor must start their on-site efforts, and complete the construction scope under this contract, within the shutdown window.
This project includes the following milestones: Milestone 1 – 60 Calendar Days after issuance of Notice to Proceed (NTP). This milestone is intended for completion of necessary submittals and RFIs, approval of shop drawings for fabrication and procurement. Milestone 2 – 4th January 2028; This milestone marks the point where access is permitted inside Kautz Road Substation yard and construction work may begin.
Milestone 3 – 31st of March 2028; This milestone marks the completion of building foundation and ready for placement of the new prefabricated control house building (provided by FermiForward). Milestone 4 – 2nd July 2029; This milestone marks the formal issuance of an Authorization for Use and Possession (AUP) of the KRS Substation facility, including all remedial work following removal of site trailers, but not including seasonal work and all final punch list items addressed..
Milestone 5 – 30th September 2029; This milestone marks the completion of the project.
Contracting contact
- Chris Daley · [email protected] · (630) 840-4256
As published on the official notice. Ask questions in writing and before any questions deadline the notice sets.
Is your business small enough?
For NAICS 237130, a business counts as small if it has no more than $45.0 million in average annual receipts (SBA size standard). This notice is set aside, so only businesses under that size, or in the named program, can bid. SBA table, current as of Oct 15, 2026.
Companies that win this kind of work
Federal contractors paid for power and communication line and related structures construction work, who also hold DOE contracts (last 12 months): possible competitors, or partners to team with.
- Crown Innovations, Inc. $37.4 million in this trade
- East Coast Powerline LLC $5.0 million in this trade
- Four Tribes Civil Construction LLC $373,652 in this trade
- Barnard Construction Company, Incorporated $-34,635 in this trade
About the buyer
The Department of Energy awarded $59.2 billion in contracts in the last 12 months; its biggest suppliers were Triad National Security, LLC, National Technology & Engineering Solutions Of Sandia, LLC and Lawrence Livermore National Security, LLC. See what DOE is buying now.
Power and Communication Line and Related Structures Construction contracts right now
There are 11 open government contract opportunities in this trade (NAICS 237130), 6 posted in the last 7 days; 55% are set aside for small businesses. The agencies buying the most are Department of the Army, Department of Energy and Departmental Offices. Most of the work with a stated place is in Illinois, Texas and Alaska. A notice in this trade gives a median of 22 days from posting to deadline; this one gives 46 days.
All open power and communication line and related structures construction contracts
Coming up in this trade
Planned contracts from the agencies' procurement forecasts, often months before a solicitation. Plans can change.
Recent awards in this trade
- Dominion Privatization Texas, LLC $61.5 million · Department of the Army · Oct 30, 2026
- DAP Construction Management LLC $9.9 million · Department of Veterans Affairs · Oct 27, 2026
- OMJ Consultant LLC $385,000 · Department of the Navy · Jul 1, 2026
- Heritage Homes LLC $5.7 million · Department of the Army · Jan 7, 2026
From the award notices agencies publish.