STATEMENT OF WORK
Project Name
Fire Control Panel Replacement
Project Number
109856
Acquisition Type
Design Build
Date
10/12/2026
Prepared by:
Reviewed by:
Carlos Guerrero, Project Manager
Jenny Ledesma, Project Director
Projects and Infrastructure Modernization Division
Projects and Infrastructure Modernization Division
Statement of Work (SOW) for Design Build
PIMD-TEMP-040
Rev.7: 02/06/2026
Doc ID: 35cdc1bcca665aa9c150e81c9c5cb37aa99391ed
REVISION HISTORY*
(Revision history for this document did not start being documented until revision no. 6) Rev No.
Rev Date
Sections
Brief Descriptions of Revisions
Sec 2.2: Weekend/Holiday Notifications
09/23/2025
Sec. 2.2, 4.4,
4.10, 4.12
Sec 4.4: Testing and Inspection turnaround
requirements
Sec 4.10: Off-site Soil Disposition
Sec 4.12: Safety Submittals review
turnaround requirements
Sec 3.2: Performance Requirements
02/06/2026
Sec. 3.2, 3.4.3,
3.4.7, 4.10
Sec. 3.4.3: Minimum Required Div 1 Specs
and Minimum Technical Specs
Sec 3.4.7: Design Schedule
Sec 4.10: Off-site Soil Disposition
Statement of Work (SOW) for Design Build
PIMD-TEMP-040
Rev.7: 02/06/2026
Doc ID: 35cdc1bcca665aa9c150e81c9c5cb37aa99391ed
1.0
Project Scope
1.1.
Background
1.2.
Project Objectives
1.3.
Project Description
1.4.
Applicable Codes and Standards
1.5.
Alternates and Options
General Requirements
2.0
2.1.
Definitions
2.2.
Coordination of Work
2.3.
Final Acceptance
3.0
Design
3.1.
Existing Site Conditions
3.2.
Design Requirements
3.3.
Review Meetings
3.4.
Design Deliverables
3.5.
Construction Support
3.6.
Commissioning
4.0
Construction
4.1.
Staging/ Parking/ Traffic Control
4.2.
Utility Deactivation
4.3.
Government Furnished Equipment (GFE)
4.4.
Services provided by LBNL
4.5.
U.S. Government and/or University Property-Materials to be Removed
4.6.
Environmental Protection
4.7.
Hazardous Materials and Restricted Items
4.8.
Construction Noise and Vibration Control
4.9.
Building Characterization
4.10. Off-site Soil Disposition Quantities and Requirements
4.11. Waste Management
4.12. Safety
5.0
Reference Documents
Statement of Work (SOW) for Design Build
PIMD-TEMP-040
Rev.7: 02/06/2026
Doc ID: 35cdc1bcca665aa9c150e81c9c5cb37aa99391ed
5.1.
Construction Details and Design Requirements (Version 0 – 9.30.24)
5.2.
Applicable Technical Specifications
5.3.
Design Deliverables Matrix (Version 2.0 – 06.30.26)
5.4.
Fire Alarm Control Panel Replacement Conceptual Design Report
5.5.
Fire Alarm As-Builts for Buildings 2, 26, 33, and 76
Statement of Work (SOW) for Design Build
The beginning of the document. Download the full file to read on.
Other documents in this bid
- B FACPR Request for Proposals Attachment B - Factor Resoponse
- C FACPR Request for Proposals Attachment C - Price Proposal
- D Subcontract FACRP
- E GPs for Fixed Price Design-Build
- F Insurance Certificate Instructions
- G Representations and Certifications Form
- H Small Business Subcontracting Plan
- FACPR Request for Proposals