University of California
Lawrence Berkeley National Laboratory
GENERAL PROVISIONS FOR FIXED PRICE DESIGN-BUILD
INDEX
1. DEFINITIONS
2. SCOPE OF SUBCONTRACT
3. PAYMENT BOND
4. PERFORMANCE BOND
5. SURETIES AND ADDITIONAL PROTECTION
6. WALSH-HEALEY PUBLIC CONTRACTS ACT
7. EXPORT CONTROL AND NOTIFICATION
8. ASSIGNMENTS
9. DISPUTES AND CLAIMS
10. NON-WAIVER OF DEFAULT
11. ENVIRONMENT, SAFETY, AND HEALTH
12. WORKER SAFETY AND HEALTH
13. ACCIDENT PREVENTION PROGRAM REQUIREMENTS
14. INJURY REPORTING
15. LIENS AND CLAIMS FOR LABOR OR MATERIALS
CLAUSE 1 – DEFINITIONS
As used herein, the following terms shall have the indicated meanings: ●
●
●
●
●
●
●
●
●
●
●
"CFR" means the U.S. Code of Federal Regulations.
"DEAR" means the DOE Acquisition Regulation.
"DOE" means the U.S. Department of Energy.
"FAR" means the Federal Acquisition Regulation.
"Government" means the United States Government.
"LBNL" means the Lawrence Berkeley National Laboratory. "Patent Counsel" means the DOE Patent Counsel.
"Subcontract" means the subcontract between the University and the Subcontractor which includes these General Provisions. "Subcontractor" means the party who has entered into this Subcontract with the University, as identified in the Subcontract. The lower-case term "subcontractor" means the Subcontractor's subcontractor(s).
"University" means The Regents of the University of California, acting through the LBNL.
CLAUSE 2 – SCOPE OF SUBCONTRACT
The scope of the Subcontract shall be limited to the acquisition of fixed price architect-engineer services and fixed price construction. The Subcontract is entered into under the University's Prime Contract No. DE-AC02-05CH11231 with DOE for management and operation of LBNL. The University is committed to doing business in a socially responsible, sustainable, and ethical manner, consistent with the University’s mission, values, and principles. As such, the University expects Subcontractors performing work for the University under this Subcontract to provide goods and services in a manner consistent with the University’s Stewardship Values including trust and respect.
CLAUSE 3 – PAYMENT BOND
For subcontracts over $150,000, before a Notice to Proceed is issued or before the Subcontractor is allowed to start work, the Subcontractor shall furnish to the University on the Laboratory's forms and naming the
The beginning of the document. Download the full file to read on.
Other documents in this bid
- A Statement of Work for Subcontract
- B FACPR Request for Proposals Attachment B - Factor Resoponse
- C FACPR Request for Proposals Attachment C - Price Proposal
- D Subcontract FACRP
- F Insurance Certificate Instructions
- G Representations and Certifications Form
- H Small Business Subcontracting Plan
- FACPR Request for Proposals