STATEMENT OF WORK (SOW) FOR
SIMPLIFIED ACQUISITION of BASE ENGINEERING REQUIREMENTS
(SABER)
HILL AIR FORCE BASE, UTAH
19 August 2026
TOC \o "1-3" \h \z \u 1PROJECT DESCRIPTION PAGEREF _Toc230075172 \h 5
1.1DEFINITION OF INSTALLATION PAGEREF _Toc230075173 \h 5
1.2PRECEDENCE PAGEREF _Toc230075174 \h 5
1.3PROJECT DESCRIPTION PAGEREF _Toc230075175 \h 5
2WORK BY THE GOVERNMENT PAGEREF _Toc230075176 \h 5
3PERFORMANCE CAPABILITIES PAGEREF _Toc230075177 \h 5
4KEY PERSONNEL PAGEREF _Toc230075178 \h 6
4.1CONTRACT MANAGER (CM) PAGEREF _Toc230075179 \h 6
4.2PROJECT MANAGER/SUPERINTENDENT PAGEREF _Toc230075180 \h 6
4.3QUALITY CONTROL OFFICER (QCO) PAGEREF _Toc230075181 \h 7
4.4ENVIRONMENTAL OFFICER PAGEREF _Toc230075182 \h 7
4.5SITE SAFETY AND HEALTH OFFICER (SSHO) PAGEREF _Toc230075183 \h 8
4.6DRAFTSMAN PAGEREF _Toc230075184 \h 8
4.7CONTRACTOR AND SUBCONTRACTOR EMPLOYEE REQUIREMENTS PAGEREF _Toc230075185 \h 8
5MANAGEMENT PLAN PAGEREF _Toc230075186 \h 10
6SUB-CONTRACTOR UTILIZATION PLAN PAGEREF _Toc230075187 \h 10
7DESIGN AND CONSTRUCTION REQUIREMENTS PAGEREF _Toc230075188 \h 10
7.1CONTRACT DOCUMENTS, REFERENCE, STANDARDS, AND PUBLICATIONS PAGEREF _Toc230075189 \h 10
7.2UNIFIED FACILITIES CRITERIA (UFC) PAGEREF _Toc230075190 \h 11
7.3INSTALLATION DESIGN STANDARDS/PLAN PAGEREF _Toc230075191 \h 11
8QUALITY CONTROL PAGEREF _Toc230075192 \h 11
8.1GENERAL PAGEREF _Toc230075193 \h 11
8.2QUALITY CONTROL PLAN CONTENTS PAGEREF _Toc230075194 \h 12
8.3QUALITY CONTROL DOCUMENTATION PAGEREF _Toc230075195 \h 12
8.4COORDINATION MEETINGS PAGEREF _Toc230075196 \h 13
9BID, PERFORMANCE AND PAYMENT BONDS PAGEREF _Toc230075197 \h 13
10PROTECTION OF CONTRACTOR’S EQUIPMENT AND GOVERNMENT PROPERTY PAGEREF _Toc230075198 \h 13
10.1FURNITURE AND EQUIPMENT PAGEREF _Toc230075199 \h 14
10.2DAMAGE TO GOVERNMENT REAL PROPERTY PAGEREF _Toc230075200 \h 14
10.3ELECTRICAL SERVICE AND COMMUNICATIONS FACILITIES PAGEREF _Toc230075201 \h 14
11PROVISIONS ON CONTRACTING OFFICER’S AUTHORITY PAGEREF _Toc230075202 \h 14
12GOVERNMENT CONTRACT ADMINISTRATION PAGEREF _Toc230075203 \h 15
13CONSTRUCTION START-UP PERIOD PAGEREF _Toc230075204 \h 15
14PRE-PERFORMANCE CONFERENCES PAGEREF _Toc230075205 \h 15
15TASK ORDERING PROCEDURES PAGEREF _Toc230075206 \h 15
15.1FAIR OPPORTUNITY PROPOSAL REQUEST (FOPR) PAGEREF _Toc230075207 \h 15
15.2SITE VISIT PAGEREF _Toc230075208 \h 16
15.3ON-SITE CONDITIONS PAGEREF _Toc230075209 \h 16
15.4PROJECT PROPOSAL PAGEREF _Toc230075210 \h 16
15.4.1CONSTRUCTION SCHEDULE PAGEREF _Toc230075211 \h 16
15.4.2DESIGN SOLUTION PAGEREF _Toc230075212 \h 17
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Solicitation Questions and Answers
- Attachment 12: Section L Instruction to Offerors
- Solicitation Questions and Answers
- Bldg 586 Seed Project FOPR Amendment 1
- Attachment 12: Section L Instruction to Offerors
- Attachment 13: Section M Evaluation Factors
- REV 1 - Seed Statement of Work Bldg 586
- SABER V Request for Information with Responses
- Attachment 3: REV 2 - Seed Statement of Work Bldg 586