Attachment 1: Statement of Work CHH P2
Updated
A PDF document (430 KB) attached to SOLICITATION NOTICE- Rochester, NY Courthouse Construction, from the Public Buildings Service. Due Oct 30, 2026, 5:00 PM (UTC-4).
File name: Attachment 1 SOW CHH P2.pdf
The full file is for paid members, or buy this bid alone.
Preview
Construction Services Statement of Work, V8.0
Courthouse Hardening Phase II, Kenneth B. Keating FOB & USCH, NY0304ZZ
U.S. General Services Administration
Capital Project Division – Northeast Division
Public Buildings Service
www.gsa.gov
Statement of Work
for
Construction Services
PROJECT IDENTIFICATION
Project Title:
Building:
Building ID #:
Building Location:
Project Control Number:
GSA Work Items:
RWA #:
Kahua Number:
SOW Author:
April 07, 2026,
Back to Top
Courthouse Hardening Phase II
Kenneth B. Keating FOB & USCH
NY0304ZZ
100 State Street
Rochester, New York
N/A
N/A
N37833560
00023059
Peter Smith
Construction Services Statement of Work, V8.0
Courthouse Hardening Phase II, Kenneth B. Keating FOB & USCH, NY0304ZZ
PROJECT INFORMATION
PROJECT SUMMARY
PROJECT BACKGROUND
CONTRACT TYPE
DELIVERY TYPE
PROJECT GOALS
Error! Bookmark not defined.
PROJECT OBJECTIVES
PROJECT SCHEDULE
SCOPE OF WORK
PROJECT REQUIREMENTS
PROJECT SITE REQUIREMENTS
STANDARDS AND CRITERIA DOCUMENTS
CUTTING & PATCHING REQUIREMENTS
NATIONAL HISTORIC PRESERVATION ACT (NHPA) REQUIREMENTS
NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) REQUIREMENTS
defined.
Error! Bookmark not
NATIONAL CAPITAL PLANNING COMMISSION (NCPC) REQUIREMENTS
U.S. COMMISSION OF FINE ARTS (CFA) REQUIREMENTS
FINE ARTS REQUIREMENTS
Error! Bookmark not defined.
ACCESSIBILITY REQUIREMENTS
SAFETY REQUIREMENTS
FIRE PROTECTION AND LIFE SAFETY REQUIREMENTS
HAZARDOUS MATERIAL REQUIREMENTS
ENERGY AND WATER EFFICIENCY REQUIREMENTS
BUILDING CONTROL SYSTEMS, INCLUDING BUILDING AUTOMATION SYSTEMS (BAS) AND
BUILDING MONITORING AND CONTROL (BMC) SYSTEMS
COMMISSIONING
SITEWORK AND STORMWATER REQUIREMENTS
BUILDING TECHNOLOGY SERVICES
April 07, 2026,
Back to Top
Error! Bookmark not defined.
Construction Services Statement of Work, V8.0
Courthouse Hardening Phase II, Kenneth B. Keating FOB & USCH, NY0304ZZ
MANUFACTURER REQUIREMENTS
BUILDING INFORMATION MODELING (BIM)
ENERGY MODELING AND PERFORMANCE
COBie
METERING
DESIGN STAGE
CONSTRUCTION STAGE
GENERAL
PERMITTING
CONSTRUCTION SCHEDULE
CONSTRUCTION PROGRESS REPORTS
SHOP DRAWINGS / PRODUCT DATA SUBMISSIONS
SCHEDULE OF INSPECTIONS AND TESTS
CONSTRUCTION INSPECTIONS
SPECIAL INSPECTIONS
COMMISSIONING
QUALITY CONTROL PLAN
CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT
SAFETY PLAN
COORDINATION OF WORK
REQUESTS FOR INFORMATION
MODIFICATIONS / CHANGE ORDERS
CONTRACT ADMINISTRATION
CONTRACTOR’S STAFF
MEETINGS
COMMUNICATION
PROJECT CLOSEOUT
SCHEDULE OF VALUES
FEE & PAYMENT
April 07, 2026,
Back to Top
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Form
- Attachment 10: Wage Determination Monroe
- Attachment 11: Safeguarding and Dissemination of Controlled Unclassified Information CUI Building Information
- Attachment 4: Keating CHH Phase 2 Pre-Bid Addendum 1
- Attachment 6: PBS Past Performance Questionnaire
- Attachment 7: Key Personnel Form
- Attachment 9: Contractors Qual and Financial Info GSA527-21a
- SBSA GC Agreement - Keating Courthouse Hardening Phase II- Construction
- Solicitation - Keating Courthouse Hardening Phase II- Construction
- Executed Solicitation Amendment 1
- Amendment 1: Keating Courthouse Hardening Phase II- Construction Request for Information RESPONSE
- Executed Solicitation Amendment 2