Massena Land Port of Entry

U.S. General Services Administration
Public Buildings Service

Statement of Work:
Project: Construct Virtual Training Facility
Location: Massena Land Port of Entry, Rooseveltown, NY
Date: 4/28/2026

1. Scope of Work:

The Contractor shall provide all labor, materials, equipment, tools, management, and full-time onsite supervision required by contract documents to construct a Virtual Training Facility at the Massena Land Port of Entry, Rooseveltown, NY. Exact work description is identified and indicated in the Contract Documents dated 7/16/2024 prepared by N. K. Bhandari. The contractor shall comply with the projects design specifications and drawings. The work will be constructed under a single prime contractor who is to adhere to all security requirements and guidelines for site access. The contractor is also to provide onsite supervision at all times work is being performed, including after-hours work as needed. The building to be constructed has a total project area is approximately 3000 SF including the 600 SF Canopy. Surrounding site work to include utilities and solar power as indicated in the design documents must also be accomplished. Contract documents indicate the work of contract, and related requirements and conditions that have an impact on the project site. Related requirements and conditions that are indicated on the contract documents include, but are not necessarily limited to, the following: 1. Existing site conditions and restrictions.
2. Requirements for use of surrounding site by Government during the work. Project Summary Description:
1. Base Bid Work: Furnish all materials, equipment, labor, and supervision to perform all work described by the contract Documents.
a. The contract work incorporates site demolition/excavation/grading/planting/paving, general construction, electrical, mechanical, plumbing, hard-wall partitions, security, and telecommunication work to meet United States Customs and Border Protection (CBP) requirements as follows:
 Selective demolition of Architectural, Mechanical and Electrical systems, construction, and finishes at nearby Building G to support the renovation work.  Mechanical, plumbing, electrical, communication, security, and fire suppression systems to serve the uses of the new facility.
 Earthwork, exterior improvements, and utilities for new facility.  Installation of common floor, wall, and ceiling finishes.  Installation of specialty floor, wall, and ceiling finishes as required.

The beginning of the document. Download the full file to read on.