DEPARTMENT OF THE ARMY

UNITED STATES ARMY INFORMATION

SYSTEMS ENGINEERING COMMAND

FORT HUACHUCA, ARIZONA 85613-5300

TECHNICAL CRITERIA

FOR THE

INSTALLATION INFORMATION

INFRASTRUCTURE ARCHITECTURE

(OUTSIDE PLANT ONLY)

BY

IMPLEMENTATION ENGINEERING

SUBJECT MATTER EXPERT

NOVEMBER 2017

FORT DETRICK ENGINEERING DIRECTORATE

Distribution C
Distribution authorized to U.S. Government agencies and their contractors only, for administrative or operational use, February 2010. Refer other requests for this document to Commander, U.S. Army Information Systems Engineering Command, ATTN: ELIE-ISE-DE, Fort Detrick, MD 21702.

Technical Criteria for the Installation Information
Infrastructure Architecture (OSP), November 2017

DISCLAIMER

The use of trade names in this document does not constitute an official endorsement or approval of the use of such
commercial hardware or software. Do not cite this document for advertisement.

CHANGES

Refer requests for all changes that affect this document to: USAISEC, ATTN: ELIE-ISE-DE, Fort Detrick, MD 217025047.

DISPOSITION INSTRUCTIONS

Destroy this document when no longer needed. Do not return it to the organization. Safeguard and destroy this document with consideration given to its classification or distribution statement requirements.

ii

Technical Criteria for the Installation Information
Infrastructure Architecture (OSP), November 2017

iii

Technical Criteria for the Installation Information
Infrastructure Architecture (OSP), November 2017

SUMMARY OF CHANGES

The following information summarizes the changes or additions to this version of the TC for I3A.
General
•

Changed release date from February 2010 to November 2017.

•

Removed Chapter 2 in its entirety. Chapter 2 in the February 2010 version of the I3A Technical Criteria was entitled “Building Telecommunications Cabling System Specifications” and provided specifications for Inside Plant (ISP) Infrastructure. In June 2016, a new Unified Facilities Criteria document was published that superseded chapter 2 of the I3A Technical Criteria. The UFC is entitled “Telecommunications Interior Infrastructure Planning and Design” (UFC 3-580-01) and is available for download at http://wbdg.org/ffc/dod/unified-facilities-criteria-ufc . Chapter 3 of this document “Outside Plant Telecommunications Cabling System Specifications” remains in effect until the Unified Facilities Criteria document for outside plant infrastructure (OSP) is published. The UFC for OSP is currently in development and will be titled “Telecommunications Exterior Infrastructure Planning and Design”