Date 24/04/26
AGL ALCMS/CCR-PMA Basic
Page
1. Customer Information
Contact Name
David Spangler
Contact Title
Electrical Maintenance Foreman
Contact Phone #
+1 757 846 6494
Contact E-Mail
2. Airport Information
IATA Code
LFI (Langley Airforce Base)
Location (State)
Hampton, VA 23665
# of Vaults
# of ATC
3. ALCMS/CCR - Advanced Preventive Maintenance
Inspection of All Computer Enclosures
Cleaning of all cooling fans, filters, and dust/debris
removal
Done
Notes
Network devices inspection
Verify proper seeding of all ethernet and
communication cables
Done
Notes
Database Evaluation and/or Repair
Check database for proper storage capacities and
backup restores
Done
Notes
Touchscreen Operational test and inspection
Touchscreen Calibration and Responsiviness test
Done
Notes
UPS testing and inspeciton
Five minute power test, remove from utility power to
verify proper alarms
Done
Notes
Printer Operational test and inspection
Create a test print, verify functionality
NA
Notes
Complete L-829 Operational testing
Testing of remote and local control and proper
feedbacks
Done
Notes
CCR Recording of Output Current, Voltage, VA, & IRMS
Data is captured and recorded by ADB SAFEGATE
ADB_Safegate - -
Done
- -
Date 24/04/26
AGL ALCMS/CCR-PMA Basic
Page
Notes
ACE/DCMU Diagnostics & Testing
Verify ACE communication, functioning overlays and
fiber connections
Done
Notes
Insulation Resistance (IRMS) Diagnostics & Testing
Verify accuracy and calibration of the IRMS module or
Done
megger card
Notes
On-site Repair (if spare parts are available)
Assist the maintenance personnel in pending repairs
when possible
Done
Notes
Spare Parts/Inventory Reccomendations
Submit parts quote request or orders if needed
NA
Notes
*Customer Representative acknowledges above PMA Completion Form carried out to, no less, than its contractual agreement by ADB SAFEGATE Representative. ADB SAFEGATE Represntative acknowledges that a detailed technical trip report will be submitted within fifteen business days of date listed below. Both, ADB SAFEGATE and Customer Representative, agree that a succesful PMA Completion Form is subject, but not limited to, inclimate weather, airport operations, escort, and/or access privileges. ADB Safegate Representative
ADB Representative Signature
Immer Adame
ADB Sign Date
2026-04-24
Customer Representative
Customer Representative Signature
Joe Gandarillas
Customer Sign Date
ADB_Safegate - -
The beginning of the document. Download the full file to read on.