Per previous Q&A # 38. It was requested to be provided as-built drawings for each discipline. It appears that only the mechanical as-builts drawings were provided. Is this to say there are no electrical as-builts available? Or if they are available, can they be provided? Available electrical drawings will be provided Per previous Q&A # 61. It was requested to understand the spare capacity in the electrical panels being used for this project and requesting those panel schedules. After reviewing the documents, I could not locate the panel schedules or drawings identifying the location of the panels. Can these schedules and locations be provided? Available electrical drawings will be provided

Does the government have any updated mechanical drawings with the latest changes recorded? One of the steam boilers has been replaced with a steam line from the central plant with a converter. No other drawings found

As there is evidence that possibly at least one of the stated boiler rooms has received modifications to the steam lines that are not shown on the as-built drawings, does the government have other as-builts showing these updates and changes? No other drawings found

The steam flow diagram shows a steam line runout to serve humidifiers. Have these humidifiers been replaced with stand-alone humidifiers or do they still need steam? No steam is used for humidification