NPS PMIS No. 231001
NPS Drwg No. 138/192565
PROJECT
IDAHO
U.S. DEPARTMENT OF THE INTERIOR
UT NP ARCH 100(2)
BRIDGES ON DELICATE ARCH ROAD
Logan
NATIONAL PARK SERVICE
Ogden 70
WYOMING
SALT
LAKE
CITY
ARCHES NATIONAL PARK
RIV
ER
Salina
COLORADO
Delta
GREEN
NEVADA
Green
River
CROSS SECTION NOTE:
Project UT NP ARCH 100(2)
Delicate Arch Road
1.
Cross Sections at Salt Wash Bridge (Sta. 31+18 - 32+18) and
Moab
Winter Camp Bridge (Sta. 37+50 - 38+50) have been removed.
R
IV
E
R
2.
Refer to the plans and staking data for slope ratios behind concrete
O
Cedar
RA
D
City
CO
LO
curb.
N
SA
J
UAN
RIVER
St. George
ARIZONA
UT NP ARCH 100(2)
UTAH KEY MAP
BRIDGES ON DELICATE ARCH ROAD
TYPE OF CONSTRUCTION:
Bridge construction, drainage, pavement, roadway realignment, rehabilitation and widening, asphalt surfacing, and safety improvements
U.S. CUSTOMARY DIMENSIONS:
Slopes are expressed as RISE:RUN
SPECIFICATIONS:
"STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND
BRIDGES ON FEDERAL HIGHWAY PROJECTS, FP-14"
11:45 AM
OF TRAN
SP
NT
E
R
IC
A
ION
AT
RT
O
DEPAR
TM
PLANS PREPARED BY
D
ST
ATES OF
R
27 July 2026
CROSS SECTIONS
E
IT
UN
N:\UT\arch100(2)\Roadway\CADD_Sheets\X-ML_Xsec\XSS-TTL.dgn
[Design IntlFt]
SCHEDULE A
Know what'sbelow.
Call
before you dig.
www.call811.com
PROJECT MANAGER
LEAD DESIGNER
HIGHWAY DESIGN MANAGER
S. DAVIS
J. FELLING
E. JESSEE
E
AM
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
DENVER, CO
SHEET
NUMBER
X0
NPS PMIS No. 231001
NPS Drwg No. 138/192565
PROJECT
UT NP ARCH 100(2)
Edge of Ex Pavement
4,290
Edge of Ex Pavement
Ex Curb Face
Edge of Ex Pavement
BRIDGES ON DELICATE ARCH ROAD
SHEET
NUMBER
X1
4,290
C
L
+2
.
%
+2
.
%
.
%
.
:
.
%
4,280
4,270
4,270
29+50.00
Subgrade = 4,284.83
Original Grnd = 4,285.38
4,290
%
.
-
+1
.
%
4,290
C
L
+2
.
%
+2
.
%
+2
.
%
.
%
.
%
4,280
4,280
29+36.00
Des Grade = 4,285.61
Subgrade = 4,284.78
11:13 AM
Des Grade = 4,285.66
Original Grnd = 4,285.56
27 July 2026
Edge of Ex Pavement
N:\UT\arch100(2)\Roadway\CADD_Sheets\X-ML_Xsec\XSS-Schedule A-4R Sections-100.dgn
[BL3 - 29+36.00 [Sheet]]
4,280
FHWA, Office of Federal Lands Highway
BRIDGES ON DELICATE ARCH ROAD
SCHEDULE A CROSS SECTIONS DELICATE ARCH ROAD
NPS PMIS No. 231001
NPS Drwg No. 138/192565
PROJECT
UT NP ARCH 100(2)
4,290
+2
.
%
Edge of Ex Pavement
Ex Curb Face
Ex Curb Face
Edge of Ex Pavement
BRIDGES ON DELICATE ARCH ROAD
C
L
+2
.
%
+2
.
%
.
%
4.
1:
.
%
.
%
[BL3 - 29+75.00 [Sheet]]
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Bid document
- UT NP ARCH 100 - Cross Sections-Option X
- UT NP ARCH 100 - Cross Sections-Option Y
- UT NP ARCH 100 Bridges on Delicate Arch Road Pavement Memo
- UT NP ARCH 100 Bridges on Delicate Arch Road-Delineators-Justification for Other Than Full and Open Competition
- UT NP ARCH100 Bridges on Delicate Arch Road Hydraulics Report Signed
- UT PRA ARCH 100 As-Builts
- QnA
- Amendment A001