CONTRACTOR PAST PERFORMANCE INFORMATION (PPI)
(The Contractor will fill out one worksheet for each reference. A minimum of three (3) references are required. Please type or print clearly.)
CONTRACTOR SUBMITTING REFERENCE:
1. Reference Company/Division Name:
2. Reference Company Physical and Mailing Address (if different):
3. Reference Company Contact (POC):
Name & Title:
Phone Number:
Email:
4. Program/Project title for similar projects that have been completed within the last three (3) years:
ATCH 10 - Contractor Past Performance Information
PACA Special Program Audits
3 November 2026
5. Contract number/solicitation number for referenced project or program (as applicable): 6. Description of the contract/project effort (please include magnitude and level of complexity as compared to our project requirements):
7. Type of contract/project – list all that apply (e.g., Firm Fixed Price, Time and Materials, Cost Plus):
8. Period of performance:
a. Original schedule:
b. Current or actual schedule:
c. Number of project scope or requirements changes over the course of the contract, up to and including product/application sustainment:
d. Primary causes of changes:
9. Contract dollar value at time of selection/closing:
a. Original project dollar value:
b. Current or actual value at time of completion:
c. Number of times it was changed:
ATCH 10 - Contractor Past Performance Information
PACA Special Program Audits
3 November 2026
d. Primary causes of changes:
10. Current or actual contract value including all changes and exercise options:
11. Current or actual completion date, and if not complete, percentage of completion:
ATCH 10 - Contractor Past Performance Information
PACA Special Program Audits
3 November 2026
The beginning of the document. Download the full file to read on.
Other documents in this bid
- ATCH 01 Instructions to Contractors Special Audits
- ATCH 03 Special Provisions
- ATCH 04 - Statement of Objectives
- ATCH 05 - Supplies Services and Prices
- ATCH 06 Evaluation Factors
- ATCH 07 Deliveries or Performances
- ATCH 08 - Contract Administration Data
- ATCH 09 Reps and Certs
- ATCH 11 NPA Agreement Sample
- ATCH 12 List of Potential Audit Locations
- ATCH 13 Historical Workload
- Offeror Letter - PACA Special Audits