FA441827R0001 Questions and Answers

4 November 2026

# Question
Can a flooring-focused contractor qualify as a prime?

Are teaming or subcontracting appropriate routes to qualify as a prime?
What are the general-contractor, licensing, bonding, insurance, past performance, and small business requirements?

Yes, but the prime contractor remains responsible for meeting all solicitation and contract requirements.
As this is a 100% small business set aside under NAICS 236220, the offeror must qualify as a small business under that classification ($45.0M annual receipts). The SOW requires contractor and subcontractor personnel to maintain licenses and certifications necessary for their assigned work classification. Bid bond of 20% or $1M is required with proposal submission. Insurance requirements have been added to Section H of the solicitation via amendment. Past performance should be recent (within past 3 years) and relevant (similar scope and complexity).

What is the anticipated contract ceiling? Anticipated task order values? Flooring-related workload?

Contract ceiling is $27.5M. Task orders are anticipated to range from $2K to $500K,Median task order value for current contract is $180K. Projected workload breakdown is included as Attachment A in the Statement of Work.
Contract ceiling is $27.5M. Task orders are anticipated to range from $2K to $500K,Median task order value for current contract is $180K. Projected workload breakdown is included as Attachment A in the Statement of Work.
Yes, but the prime contractor remains responsible for meeting all contract requirements.

Answer
Yes. However, past performance demonstrating competency in all 3 areas (floor covering, protective coating, misc. repairs) will be evaluated more favorably than past performance demonstrating competency in only 1 or 2 areas.

What is the anticipated total contract ceiling and estimated annual task-order volume for this IDIQ?

Are prime contractors permitted to utilize qualified subcontractors for specialized flooring, painting, mechanical, electrical, and plumbing work, subject to applicable subcontracting limitations?

Will relevant past performance from proposed teaming partners or 7 subcontractors be considered during proposal evaluation?

Yes, but the prime contractor's past performance will be given greater consideration.

Are there specific bonding, financial-capacity, or self-performance 8 requirements that prospective prime contractors should address?

Bid bond of 20% of the base year price or $1M (whichever is less) is

The beginning of the document. Download the full file to read on.