Bid document
Updated
A PDF document (856 KB) attached to WWYK250063 - Install React VII Facility, B9001, Post V19, from the Department of the Air Force. Due Nov 2, 2026, 2:00 PM (UTC-6).
File name: 01 33 00.pdf
The full file is for paid members, or buy this bid alone.
Preview
Tinker AFB
Tinker General Requirements
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1
1.1
1.1.1
GENERAL
SUMMARY
Submittal Information
The Contracting Officer and/or the Contracting Officer's Representative may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2
Project Type
The Contractor's Quality Control (QC) Manager and the Designer of Record (DOR), if applicable, are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
1.1.3
Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2
1.2.1
DEFINITIONS
Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
November 2022
Section 01 33 00
Tinker AFB
Tinker General Requirements
Certificates Of Insurance
Surety Bonds
List of Proposed Subcontractors
Baseline Schedule
Submittal Register
Schedule of Prices or Earned Value Report
Accident Prevention Plan
Work Plan
Quality Control (QC) Plan
The beginning of the document. Download the full file to read on.