S TATEMENT O F W ORK

FOR

C40 & C41 RF ROOF REPLACEMENT

CONSTRUCTION

CAT: ☐A1 ☐ A2 ☒ A3

REVISION 1

DATED: August 28th, 2026

Jaspreet Sidhu

Digitally signed by Jaspreet Sidhu
DN: C=US, [email protected],
O=PPPL, OU=PMO, CN=Jaspreet
Sidhu
Reason: I have reviewed this
document
Date: 2026.09.16 13:22:19-04'00'

Cognizant Individual
Digitally signed by Kyle Jacobs
DN: C=US, [email protected],

O=PPPL, OU=F&SS, CN=Kyle

Jacobs
Date: 2026.10.01 09:24:41-04'00'

Responsible Engineer
Digitally signed by Robert S. Oh
DN: C=US, [email protected],

OU=Facilities and Site
Robert S. Oh O=PPPL,
Services, CN=Robert S. Oh

Date: 2026.10.01 15:28:32-04'00'

Responsible Engineer
Digitally signed by Joy E.

Joy E. Fleming, Fleming, MPH, CIH, CSP
2026.10.02 10:15:30

MPH, CIH, CSP Date:

-04'00'
ES&H
Digitally signed by
Marlo
Marlo Ramos
Date: 2026.10.02
Ramos
10:38:35 -04'00'

Quality Assurance

Jermain Lewis

Digitally signed by Jermain Lewis
DN: C=US, [email protected],
O=PPPL - Design and Construction, OU=Project
Managment Office, CN="Jermain Lewis "
Location: Fire Alarm
Reason: I attest to the accuracy and integrity of
this document
Date: 2026.10.06 10:48:38-04'00'

Project Manager (PM)

PRINCETON UNIVERSITY

PLASMA PHYSICS LABORATORY

P.O. BOX 451

PRINCETON, N.J. 08543

609-243-2000

1.0 INTRODUCTION & SCOPE

1.1. INTRODUCTION

1.1.1. The Princeton Plasma Physics Laboratory (PPPL) is used to house, operate, and maintain advanced experimental equipment and infrastructure critical to the mission of the Laboratory. 1.1.2. There are several existing roofs (C40 RF Building & C41 CS Building) which are past their useful life requiring costly maintenance to upkeep. Severe water infiltration occurs regularly at failing joints, punctures, and flashing. Portions of existing metal coping have pulled away during storm events causing large sections of membrane to separate from the substrate. A catastrophic failure to one of these roofs would negatively impact the ability to conduct the top priority experimental operations in the Laboratory.

1.2. SCOPE

1.2.1. The Subcontractor shall provide all materials, labor, supervision, equipment, and expertise required to replace the noted roofs and specified components per the associated contract design documents. Construction scope includes the following: 1.2.1.1.

Remove and replace existing built-up roofs at PPPL. Buildings include:

The beginning of the document. Download the full file to read on.